Milestone Extension: Section 408 Permit

Submitted by craig.litteken… on

The Section 408 milestones are dependent on BOEM’s EIS action milestones. A shift of BOEM’s EIS action milestones by 417 days results in a commensurate shift to the Section 408 action milestones.

 In addition to the shift to the schedule to address the EIS, USACE is also requesting to move the Section 408 Complete application submitted (Applicant Action) Milestone. The USACE now calculates this date as 60 days before the ROD is issued by BOEM. USACE has refined this milestone definition based on lessons learned from earlier applicants. Therefore, an extension of the Section 408 milestones is requested based upon the extension of BOEM’s COP and EIS milestones

Action
Project Name: Responsible Agency:
US Army Corps of Engineers - Civil Works
Agency Status: Cooperating under FAST-41
Cooperating under NEPA
Status:
Planned
POC Name:
Ann Marie DiLorenzo, North Atlantic Division
POC Title:
Section 408 FAST-41 Dashboard Administrator

Description:

A Section 408 Permission is required from the US Army Corps of Engineers pursuant to Section 14 of the Rivers and Harbors Act of 1899, 33 U.S.C. 408 (Section 408) and the Corps will evaluate the proposed activity relative to the nearby US Army Corps of Engineers Civil Works Projects and assets. 

Milestones:

Initial application submitted (Applicant Action)
Current Target Date:
Completeness Determination (Agency Action)
Current Target Date:
Complete application submitted (Applicant Action)
Current Target Date:
Issuance of Decision (Agency Action)
Current Target Date:
Milestone
Issuance of Decision (Agency Action)
Current Target Date:
Project

PROJECT WEBSITE: Skipjack Wind

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING

0 out of 0

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Renewable Energy Production

SECTOR
Renewable Energy Production

Project Category

CATEGORY
Project Category FAST-41 Covered Projects

Department of the Interior

LEAD AGENCY
Department of the Interior, Bureau of Ocean Energy Management

View FAST-41 Postings by Agencies

Description:

Skipjack Offshore Energy, LLC (SJOE) intends to develop, build, operate, and own (through one or more affiliated special purpose entities) an offshore wind farm located approximately 15 miles off the coast of Delaware within Lease Areas OCS A0519 and OCS A0482. The purpose of the Project is to construct and operate a new offshore wind farm designed to help one or more states within the mid-Atlantic region meet their clean energy goals. The Project would consist of up to 72 wind turbine generators (“WTG”), associated inter-array cabling, new onshore and offshore substations, transmission cables and onshore works for connection to the wholesale electric grid administered by PJM Interconnection L.L.C.

 

The Executive Director granted a Bureau of Ocean Energy Management request to extend completion dates for all actions on March 24, 2025. The Executive Director determination is posted here.

field_status
System Comments
Furthest out
Original Target Date: 11/09/2027
Milestone: Issuance of Decision (Agency Action)

Requested extensions greater than 30 days for this Action are shown below:

Issuance of Decision (Agency Action) extended by 665
From: 07/12/2028
To: 09/04/2029
Approver Comments
BOEM submitted an Executive Director Determination Request to update the project schedule, but since that time, the project sponsor has withdrawn the project from FAST-41. Therefore, the milestone extension request is not needed and is rejected.
Missed Date Process
No
Missed Date Triggered by Extension
No
Original Milestone
Issuance of Decision (Agency Action)
Current Target Date:
Furthest Original Target Date Milestone
Issuance of Decision (Agency Action)
Current Target Date: