Permitting Action Modification History

Cancelled
The Section 408 milestones are dependent on BOEM’s EIS action milestones. A shift of BOEM’s EIS action milestones by 417 days results in a commensurate shift to the Section 408 action milestones.  In addition to the shift to the schedule to address the EIS, USACE is also requesting to move the Section 408 Complete application submitted (Applicant Action) Milestone. The USACE now calculates this date as 60 days before the ROD is issued by BOEM. USACE has refined this milestone definition based on lessons learned from earlier applicants. Therefore, an extension of the Section 408 milestones is requested based upon the extension of BOEM’s COP and EIS milestones , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 06-22-2026 03-22-2027 --- No
Completeness Determination (Agency Action) 07-22-2026 04-21-2027 --- No
Complete application submitted (Applicant Action) 09-21-2026 02-11-2028 --- No
Issuance of Decision (Agency Action) 11-09-2027 07-12-2028 --- No
Planned
BOEM is requesting these completion date modifications due to the timing of the Project Sponsor’s submission of a revised Construction and Operations Plan (COP) containing additional data and assessments that BOEM requires prior to issuing a Notice of Intent (NOI) to prepare an Environmental Impact Statement (EIS) under NEPA. BOEM has requested that the revised COP contain certain survey data for one of the proposed cable routes as well as the following assessments: the Navigational Safety Risk Assessment; Historic Resources Visual Effects Assessment for certain facilities; Marine Archaeological Resource Assessment for a particular cable route; and the Terrestrial Archeological Resource Assessment for all routes and facilities in the onshore project design envelope. The Project Sponsor intends to submit the revised COP containing all the requested information on October 27, 2025.  The Section 408 final completion date is dependent upon the final completion date of BOEM’s NEPA action. USACE requests a review of 90 days between issuance of the ROD and issuance of USACE’s decisions. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 06-22-2026 03-22-2027 --- No
Completeness Determination (Agency Action) 07-22-2026 04-21-2027 --- No
Complete application submitted (Applicant Action) 09-21-2026 02-11-2028 --- No
Issuance of Decision (Agency Action) 11-09-2027 07-12-2028 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 06-22-2026 06-22-2026 --- No
Completeness Determination (Agency Action) 07-22-2026 07-22-2026 --- No
Complete application submitted (Applicant Action) 09-21-2026 09-21-2026 --- No
Issuance of Decision (Agency Action) 11-09-2027 11-09-2027 --- No