Milestone Extension: Section 408 Permit

Submitted by cori.carraway@… on

Due to updates to BOEM's schedule, all 408 milestone dates were adjusted to line up with the new dates

Action
Project Name: Responsible Agency:
US Army Corps of Engineers - Civil Works
Agency Status: Cooperating under FAST-41
Status:
Planned
POC Name:
Mike Anderson
POC Title:
Chief, Design Section, Operations Branch, Norfolk District, USACE

Description:

A Section 408 Permission may be required from the Norfolk District pursuant to Section 14 of the Rivers and Harbors Act of 1899, 33 U.S.C. 408 (Section 408). It is marked as a Section 408 requirement until the applicant can provide adequate documents that would support a proper evaluation of the proposed activity relative to the nearby US Army Corps of Engineers Civil Works Projects and assets. 

Milestones:

Initial application submitted (Applicant Action)
Current Target Date:
Milestone Details

A Section 408 Permission may be required from pursuant to Section 14 of the Rivers and Harbors Act of 1899, 33 U.S.C. 408 (Section 408). It is marked as a Section 408 requirement until the applicant can provide adequate documents that would support a proper evaluation of the proposed activity relative to any nearby US Army Corps of Engineers Civil Works Projects and assets. 

Completeness Determination (Agency Action)
Current Target Date:
Complete application submitted (Applicant Action)
Current Target Date:
Issuance of Decision (Agency Action)
Current Target Date:
Milestone Details

Issuance of a Section 408 permission will be subject to contingencies, including but not limited to, completion of the project NEPA documentation/Record of Decision. Should submission of any required information be delayed, the District reserves its right to adjust the Decision Date as necessary.

Milestone
Issuance of Decision (Agency Action)
Current Target Date:
Milestone Details

Issuance of a Section 408 permission will be subject to contingencies, including but not limited to, completion of the project NEPA documentation/Record of Decision. Should submission of any required information be delayed, the District reserves its right to adjust the Decision Date as necessary.

Project

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING

0 out of 0

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Renewable Energy Production

SECTOR
Renewable Energy Production

Project Category

CATEGORY
Project Category FAST-41 Covered Projects

Department of the Interior

LEAD AGENCY
Department of the Interior, Bureau of Ocean Energy Management

View FAST-41 Postings by Agencies

Description:

Update: In June 2022, the project name changed from Kitty Hawk Wind Project to Kitty Hawk North Wind Project to reflect the segmenting of the project.

The purpose of the Kitty Hawk North Wind Project is to develop a commercial-scale, offshore wind energy facility in Commercial Lease OCS-A 0508 offshore North Carolina, with up to 69 total wind turbine generators, 1 offshore substation (also called “electrical service platform”), inter-array cables, 1 onshore substation, and up to 2 transmission cables making landfall in Virginia Beach, Virginia, and connecting to the Pennsylvania-New Jersey-Maryland (PJM) Interconnection energy grid. Kitty Hawk is actively seeking one or more power purchase agreement awards for this project. The project is intended to substantially contribute to the region’s electrical reliability and help Virginia achieve its renewable energy goals as stated in the Virginia Clean Economy Act.

FAST-41 provides increased transparency and predictability by requiring Federal agencies to publish comprehensive permitting timetables for all "covered" projects, and provides clear procedures for modifying permitting timetables to address the unpredictability inherent in the environmental review and permitting process for significant infrastructure projects. For more information, see "The FAST-41 Process" at  https://www.permits.performance.gov/fpisc-content/fast-41-process. 

field_status
System Comments
Furthest out
Original Target Date: 11/01/2023
Milestone: Issuance of Decision (Agency Action)

Requested extensions greater than 30 days for this Action are shown below:

Issuance of Decision (Agency Action) extended by 608
From: 05/28/2024
To: 07/01/2025
Approver Comments
ED Review completed and final signed 5/12/2023.
Missed Date Process
No
Missed Date Triggered by Extension
No
Original Milestone
Issuance of Decision (Agency Action)
Current Target Date:
Furthest Original Target Date Milestone
Issuance of Decision (Agency Action)
Current Target Date:
Milestone Details

Issuance of a Section 408 permission will be subject to contingencies, including but not limited to, completion of the project NEPA documentation/Record of Decision. Should submission of any required information be delayed, the District reserves its right to adjust the Decision Date as necessary.