Permitting Action Modification History

Cancelled
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 09-01-2022 06-11-2025 --- No
Completeness Determination (Agency Action) 03-24-2023 07-11-2025 --- No
Complete application submitted (Applicant Action) 09-30-2022 09-09-2025 --- No
Issuance of Decision (Agency Action) 11-01-2023 09-15-2026 --- No
Planned
The changes to the PDE as described above will need to be analyzed and considered by USACE as part of their permitting processes. In addition, the Section 10/404 final completion date is dependent upon the final completion date of BOEM’s NEPA action. For this project, the USACE review will require 120 days between issuance of the ROD and issuance of USACE’s Section 10/404 decision. Therefore, an extension of the Section 10/404 final completion date is requested based upon the extension of the NEPA completion date. The Section 408 review is anticipated to conclude on the same date as Section10/404 action. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 09-01-2022 06-11-2025 --- No
Completeness Determination (Agency Action) 03-24-2023 07-11-2025 --- No
Complete application submitted (Applicant Action) 09-30-2022 09-09-2025 --- No
Issuance of Decision (Agency Action) 11-01-2023 09-15-2026 --- No
Planned
Due to updates to BOEM's EIS schedule, to include NOA and ROD dates, all 408 milestone dates were adjusted. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 09-01-2022 03-27-2024 --- No
Completeness Determination (Agency Action) 03-24-2023 04-26-2024 --- No
Complete application submitted (Applicant Action) 09-30-2022 06-25-2024 --- No
Issuance of Decision (Agency Action) 11-01-2023 07-01-2025 --- No
Planned
Original Target Date Entry Effort , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 09-01-2022 02-22-2023 --- No
Completeness Determination (Agency Action) 03-24-2023 03-24-2023 --- No
Complete application submitted (Applicant Action) 09-30-2022 03-10-2023 --- No
Issuance of Decision (Agency Action) 11-01-2023 05-28-2024 --- No
Planned
The Milestones are moving to align with changes in submission dates. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 09-01-2022 02-22-2023 --- No
Complete application submitted (Applicant Action) 03-10-2023 03-10-2023 --- No
Completeness Determination (Agency Action) 03-24-2023 03-24-2023 --- No
Issuance of Decision (Agency Action) 11-01-2023 05-28-2024 --- No