Milestone Extension: Section 408 Permit

Submitted by jennifer.malla… on

A shift to the Section 408 decision date is required due to delays to the Section 106 consultation and Record of Decision (ROD) dates. The timeframe for this 408 decision is 90 days after BOEM releases the ROD. 

Action
Project Name: Responsible Agency:
US Army Corps of Engineers - Civil Works
Agency Status: Cooperating under FAST-41
Cooperating under NEPA
Status:
In Progress
POC Name:
Juan Carlos Corona
POC Title:
Design Manager - Section 408 Coordinator

Description:

A Section 408 Permission is required pursuant to Section 14 of the Rivers and Harbors Act of 1899, 33 U.S.C. 408 (Section 408). 

Milestones:

Initial application submitted (Applicant Action)
Completed Date:
Milestone Details

Milestone target date based on the proponent submitting the initial permit application 30 days prior to BOEM's anticipated issuance of the draft EIS.

Completeness Determination (Agency Action)
Completed Date:
Complete application submitted (Applicant Action)
Completed Date:
Issuance of Decision (Agency Action)
Current Target Date:
Milestone Details

The target is scheduled 90 days after BOEM's target date for Issuance of a Record of Decision. Should the BOEM ROD decision change, the Corps permit decision date would be adjusted accordingly to allow for the full 90 day review period. Also, should submission of any required information be delayed, the district reserves its right to adjust this Target Completion Date as necessary.

The Section 10/404 and Section 408 decisions will be issued jointly. 

Milestone
Issuance of Decision (Agency Action)
Current Target Date:
Milestone Details

The target is scheduled 90 days after BOEM's target date for Issuance of a Record of Decision. Should the BOEM ROD decision change, the Corps permit decision date would be adjusted accordingly to allow for the full 90 day review period. Also, should submission of any required information be delayed, the district reserves its right to adjust this Target Completion Date as necessary.

The Section 10/404 and Section 408 decisions will be issued jointly. 

Project

PROJECT WEBSITE: Ocean Wind

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
SUBJECT TO CHANGE

9 out of 10

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Renewable Energy Production

SECTOR
Renewable Energy Production

Project Category

CATEGORY
Project Category FAST-41 Covered Projects

Department of the Interior

LEAD AGENCY
Department of the Interior, Bureau of Ocean Energy Management

View FAST-41 Postings by Agencies

Other Agencies with Actions or Authorizations:

Department of the Army

Department of the Army, US Army Corps of Engineers - Regulatory

Department of Commerce

Department of Commerce, National Oceanic and Atmospheric Administration

Department of the Interior

Department of the Interior, Fish and Wildlife Service

Environmental Protection Agency

Environmental Protection Agency

Department of the Army

Department of the Army, US Army Corps of Engineers - Civil Works

Description:

Ocean Wind, LLC intends to construct, operate and maintain a commercial-scale offshore wind energy facility located approximately 15 miles off the coast of New Jersey within  Lease Area OCS-A 0498 (the “Ocean Wind 1 Project”). The Ocean Wind 1 Project, consisting of up to 98 wind turbine generators (WTG), inter-array cables, up to three Offshore Substations (OSS), two onshore substations, and two transmission cable routes making landfall in Ocean County, New Jersey and Cape May County, New Jersey,  is intended to fulfill the New Jersey Board of Public Utilities’ (BPU) September 20, 2018, solicitation for 1,100 MW of offshore wind capacity, and a corresponding Offshore Wind Renewable Energy Certificate (OREC) allowance of 4,851,489 MW-hours per year was awarded to Ocean Wind via BPU on June 21, 2019 (BPU Docket No. QO18121289, In the Matter of the Board of Public Utilities Offshore Wind Solicitation for 1,100 MW – Evaluation of the Offshore Wind Applications). The Ocean Wind 1 Project would contribute to New Jersey’s goal of 7.5 gigawatts (GW) of offshore wind energy generation by 2035 as outlined in New Jersey Governor’s Executive Order No. 92, issued on November 19, 2019. 

Update: 

The Executive Director granted a Bureau of Ocean Energy Management (BOEM) request to extend the Endangered Species Act Consultation completion date on September 23, 2022. The Executive Director determination is posted here.

The Executive Director granted a Bureau of Ocean Energy Management (BOEM) request to extend the EFH consultation and Endangered Species Act Consultation completion date on November 18, 2022. The Executive Director determination is posted here.

The Executive Director granted a Bureau of Ocean Energy Management (BOEM) request to extend the Endangered Species Act Consultation completion date on December 16, 2022. The Executive Director determination is posted here.

The Executive Director granted a Bureau of Ocean Energy Management (BOEM) request to extend the Construction and Operations Plan, Environmental Impact Statement, and Section 106 completion date on January 31, 2023. The Executive Director determination is posted here.

field_status
System Comments
Furthest out
Original Target Date: 07/13/2023
Milestone: Issuance of Decision (Agency Action)

Requested extensions greater than 30 days for this Action are shown below:

Issuance of Decision (Agency Action) extended by 84
From: 07/13/2023
To: 10/05/2023
Approver Comments
ED determination signed on 4/21/23.
Missed Date Process
No
Missed Date Triggered by Extension
No
Original Milestone
Issuance of Decision (Agency Action)
Current Target Date:
Milestone Details

The target is scheduled 90 days after BOEM's target date for Issuance of a Record of Decision. Should the BOEM ROD decision change, the Corps permit decision date would be adjusted accordingly to allow for the full 90 day review period. Also, should submission of any required information be delayed, the district reserves its right to adjust this Target Completion Date as necessary.

The Section 10/404 and Section 408 decisions will be issued jointly. 

Furthest Original Target Date Milestone
Issuance of Decision (Agency Action)
Current Target Date:
Milestone Details

The target is scheduled 90 days after BOEM's target date for Issuance of a Record of Decision. Should the BOEM ROD decision change, the Corps permit decision date would be adjusted accordingly to allow for the full 90 day review period. Also, should submission of any required information be delayed, the district reserves its right to adjust this Target Completion Date as necessary.

The Section 10/404 and Section 408 decisions will be issued jointly.