Permitting Action Modification History

Complete
USACE completed the milestone ahead of schedule, on 10/3/23. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 04-27-2022 04-27-2022 --- Yes
Completeness Determination (Agency Action) 05-27-2022 05-27-2022 --- Yes
Complete application submitted (Applicant Action) 05-27-2022 05-27-2022 --- Yes
Issuance of Decision (Agency Action) 07-13-2023 10-03-2023 --- Yes
In Progress
A shift to the Section 408 decision date is required due to delays to the Section 106 consultation and Record of Decision (ROD) dates. The timeframe for this 408 decision is 90 days after BOEM releases the ROD.  , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 04-27-2022 04-27-2022 --- Yes
Completeness Determination (Agency Action) 05-27-2022 05-27-2022 --- Yes
Complete application submitted (Applicant Action) 05-27-2022 05-27-2022 --- Yes
Issuance of Decision (Agency Action) 07-13-2023 10-05-2023 --- No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 04-27-2022 04-27-2022 --- Yes
Completeness Determination (Agency Action) 05-27-2022 05-27-2022 --- Yes
Complete application submitted (Applicant Action) 05-27-2022 05-27-2022 --- Yes
Issuance of Decision (Agency Action) 07-13-2023 07-13-2023 --- No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 04-27-2022 04-27-2022 --- Yes
Completeness Determination (Agency Action) 05-27-2022 05-27-2022 --- Yes
Issuance of Decision (Agency Action) 07-13-2023 07-13-2023 --- No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 04-27-2022 04-27-2022 --- Yes
Completeness Determination (Agency Action) 05-27-2022 05-27-2022 --- No
Issuance of Decision (Agency Action) 07-13-2023 07-13-2023 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) --- 04-27-2022 --- No
Completeness Determination (Agency Action) --- 05-27-2022 --- No
Issuance of Decision (Agency Action) --- 07-13-2023 --- No