USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Portions of this site may be affected due to a lapse in appropriations and associated shutdown/furloughs. Please monitor this page for updates on site availability and operating status.

Milestone Extension: Section 106 Review

Submitted by cori.carraway@… on

The COP for this project was initially filed with BOEM in December 2020, and an NOI was
published in the Federal Register in July 2021. BOEM is currently working towards a Draft
Environmental Impact Statement milestone in 2024.

The NEPA schedule is delayed primarily due to the project sponsor changing the design envelope of the
project such that changes will need to be made to the analyses supporting the NEPA review, consultations, and permits. The project sponsor plans to submit an updated Construction and Operation Plan (COP) to BOEM in March. The PDE changes include a reduction in number of turbines and the Wind Development Area, a change to the onshore cable route parameters, and information on accommodating a layout which complies with a request from DOD that will be analyzed as an alternative in the DEIS. The project sponsor is making these changes primarily to eliminate overlap between their Kitty Hawk North and South projects. The estimated turbine reduction for Kitty Hawk North is from 69 turbines initially proposed to 55 turbines. BOEM must have this new information in
order to complete the Draft Environmental Impact Statement (DEIS) and the Biological Assessment (BA).

For Section 106: the changes to the PDE as described above will need to be analyzed and considered as
part of the Section 106 consultation.

Action
Project Name: Responsible Agency:
Bureau of Ocean Energy Management
Status:
In Progress
POC Name:
Laura K Schnitzer
POC Title:
Archaeologist/Program Tribal Liaison Officer
POC Email:
SHPO:

North Carolina
Virginia

Milestones:

Consultation initiated with SHPO/THPO (Agency Action)
Completed Date:
Notification agency will use NEPA substitution approach [36 CFR 800.8(c)] (Agency Action)
Completed Date:
Section 106 consultation concluded (Agency Action)
Current Target Date:
Milestone
Section 106 consultation concluded (Agency Action)
Current Target Date:
Project

PROJECT WEBSITE: Kittyhawkoffshore

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING

0 out of 0

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Renewable Energy Production

SECTOR
Renewable Energy Production

Project Category

CATEGORY
Project Category FAST-41 Covered Projects

Department of the Interior

LEAD AGENCY
Department of the Interior, Bureau of Ocean Energy Management

View FAST-41 Postings by Agencies

Description:

Update: In June 2022, the project name changed from Kitty Hawk Wind Project to Kitty Hawk North Wind Project to reflect the segmenting of the project.

The purpose of the Kitty Hawk North Wind Project is to develop a commercial-scale, offshore wind energy facility in Commercial Lease OCS-A 0508 offshore North Carolina, with up to 69 total wind turbine generators, 1 offshore substation (also called “electrical service platform”), inter-array cables, 1 onshore substation, and up to 2 transmission cables making landfall in Virginia Beach, Virginia, and connecting to the Pennsylvania-New Jersey-Maryland (PJM) Interconnection energy grid. Kitty Hawk is actively seeking one or more power purchase agreement awards for this project. The project is intended to substantially contribute to the region’s electrical reliability and help Virginia achieve its renewable energy goals as stated in the Virginia Clean Economy Act.

 

The Executive Director granted a Bureau of Ocean Energy Management request to extend the EIS, COP, Section 106, Section 10/404/408, and OCS air permit completion dates on May 12, 2023. The Executive Director determination is posted here.

field_status
System Comments
Furthest out
Original Target Date: 08/03/2023
Milestone: Section 106 consultation concluded (Agency Action)

Requested extensions greater than 30 days for this Action are shown below:

Section 106 consultation concluded (Agency Action) extended by 1019
From: 03/03/2025
To: 05/18/2026
Approver Comments
EDD granted - signed 3/25/2024
Missed Date Process
No
Missed Date Triggered by Extension
No
Original Milestone
Section 106 consultation concluded (Agency Action)
Current Target Date:
Furthest Original Target Date Milestone
Section 106 consultation concluded (Agency Action)
Current Target Date: