USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Milestone Extension: Section 106 Review

Submitted by craig.litteken… on

The project sponsor presented new project information last fall on October 13, 2022, to BOEM, NOAA,
and USACE. The change in design for feasible wind turbine generator (WTG) locations involved removing 21 WTGs for the project. This change required additional analysis by BOEM for a new constructible preferred alternative that needed to be added to FEIS. The project design changed the impacts analysis for consultations.  This action is dependent upon the ROD.

Action
Project Name: Responsible Agency:
Bureau of Ocean Energy Management
Status:
In Progress
POC Name:
Sarah Stokely
POC Title:
Lead Historian

Milestones:

Consultation initiated with SHPO/THPO (Agency Action)
Completed Date:
Notification agency will use NEPA substitution approach [36 CFR 800.8(c)] (Agency Action)
Completed Date:
Section 106 consultation concluded (Agency Action)
Current Target Date:
Milestone
Section 106 consultation concluded (Agency Action)
Current Target Date:
Project

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
11/20/2023

9 out of 9

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Renewable Energy Production

SECTOR
Renewable Energy Production

Project Category

CATEGORY
Project Category FAST-41 Covered Projects

Department of the Interior

LEAD AGENCY
Department of the Interior, Bureau of Ocean Energy Management

View FAST-41 Postings by Agencies

Other Agencies with Actions or Authorizations:

Department of Commerce

Department of Commerce, National Oceanic and Atmospheric Administration

Department of the Army

Department of the Army, US Army Corps of Engineers - Regulatory

Environmental Protection Agency

Environmental Protection Agency

Department of the Interior

Department of the Interior, Fish and Wildlife Service

Description:

Revolution Wind LLC proposes the Revolution Wind Farm Project, an offshore wind farm to be located approximately 12 statute miles south of the coast of Rhode Island in federal waters in the area designated by the U.S. Bureau of Ocean Energy Management (BOEM) as Renewable Energy Lease Number OCS-A 0486 (the Project).

The purpose of the Project is to provide clean, reliable offshore wind energy that will increase the amount and availability of renewable energy to New England consumers while creating the opportunity to displace electricity generated by fossil fuel-powered plants and offering substantial economic and environmental benefits to the New England region. Massachusetts, Rhode Island, Connecticut, and New York have adopted substantial renewable portfolio standards and clean energy targets to address issues associated with climate change, highlighting the current and future demand for this Project.

The Project has been awarded three Power Purchase Agreements (PPAs) totaling 704 MW of generation capacity: 1) a 200 MW contract with the State of Connecticut approved in December 2018; 2) a 400 MW contract with the State of Rhode Island approved in February 2019; and 3) a 104 MW contract with the State of Connecticut approved in November 2019. The Project is being developed to fulfill its obligations to Connecticut and Rhode Island in accordance with the PPAs. The Project maximum generating capacity is 880 MW.

Update:

The Executive Director granted a Bureau of Ocean Energy Management request to extend Environmental Impact Statement, Construction and Operations Plan, and Section 106 Consultation completion dates. The Executive Director determination is posted here.

field_status
System Comments
Furthest out
Original Target Date: 05/01/2023
Milestone: Section 106 consultation concluded (Agency Action)

Requested extensions greater than 30 days for this Action are shown below:

Section 106 consultation concluded (Agency Action) extended by 112
From: 07/07/2023
To: 08/21/2023
Approver Comments
ED determination signed on 5/31/23.
Missed Date Process
No
Missed Date Triggered by Extension
No
Original Milestone
Section 106 consultation concluded (Agency Action)
Current Target Date:
Furthest Original Target Date Milestone
Section 106 consultation concluded (Agency Action)
Current Target Date: