Permitting Action Modification History

Complete
Sec 106 concluded on Aug 18, prior to the anticipated completion date of Aug 21. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Consultation initiated with SHPO/THPO (Agency Action) 04-30-2021 04-30-2021 --- Yes
Notification agency will use NEPA substitution approach [36 CFR 800.8(c)] (Agency Action) 04-06-2021 04-06-2021 --- Yes
Section 106 consultation concluded (Agency Action) 05-01-2023 08-18-2023 --- Yes
In Progress
The project sponsor presented new project information last fall on October 13, 2022, to BOEM, NOAA, and USACE. The change in design for feasible wind turbine generator (WTG) locations involved removing 21 WTGs for the project. This change required additional analysis by BOEM for a new constructible preferred alternative that needed to be added to FEIS. The project design changed the impacts analysis for consultations.  This action is dependent upon the ROD. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Consultation initiated with SHPO/THPO (Agency Action) 04-30-2021 04-30-2021 --- Yes
Notification agency will use NEPA substitution approach [36 CFR 800.8(c)] (Agency Action) 04-06-2021 04-06-2021 --- Yes
Section 106 consultation concluded (Agency Action) 05-01-2023 08-21-2023 --- No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Consultation initiated with SHPO/THPO (Agency Action) 04-30-2021 04-30-2021 --- Yes
Notification agency will use NEPA substitution approach [36 CFR 800.8(c)] (Agency Action) 04-06-2021 04-06-2021 --- Yes
Section 106 consultation concluded (Agency Action) 05-01-2023 07-07-2023 --- No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Consultation initiated with SHPO/THPO (Agency Action) 04-30-2021 04-30-2021 --- Yes
Notification agency will use NEPA substitution approach [36 CFR 800.8(c)] (Agency Action) 04-06-2021 04-06-2021 --- Yes
Section 106 consultation concluded (Agency Action) 05-01-2023 05-01-2023 --- No