The milestone was changed in accordance with BOEM's updated schedule.
Cooperating under NEPA
Description:
Department of Army authorization from the US Army Corps of Engineers Philadelphia District is required pursuant to Section 10 of the Rivers and Harbors Act of 1899 and Section 404 of the Clean Water Act. Activities that require authorization include: Installation of turbine structures on monopole supports embedded in the ocean floor. Water jet installed export cable(s). Monopole supported offshore substation(s). The trenching of ocean bottom within 3 nautical miles of the state of New Jersey for the placement of export cable(s). Horizontal directional drilling beneath the shoreline for the export cable to begin its path to a planned substation/grid connection. The export cable will either be above or below ground after landing, planned to follow road beds. An aquatic resource delineation and jurisdictional determination will be required for the onshore portion of the export cable, especially where assumed 404 jurisdiction is suspected. Possible non tidal and/or tidal wetland impacts will occur if the cable is to remain above ground for any portion of its path to the proposed substation. Construction of a new substation is potentially necessary to tie the wind generated energy into the existing power grid. The substation may require impacts to non tidal and/or tidal wetlands.
Milestones:
The agreed upon timetable has the proponent submitting the initial permit application 30 days prior to BOEM's anticipated issuance of the draft EIS.
The Corps anticipates working closely with the sponsor to ensure the initial application contains all the
items needed for a complete application. It is anticipated that any completeness items needed after the
initial submittal will be received within 15 days of the initial submittal.
Application determined complete on 11 May 22.
The Corps issued a 30-day public notice on June 17, 2022, accepting public comments on the Section 10 Rivers and Harbors Act and Section 404 Clean Water Act permit application. The public notice, including information on how to submit comments, can be found here: https://www.nap.usace.army.mil/Missions/Regulatory/Public-Notices/Article/3066660/2017-00135-84/.
-
Environmental Impact Statement (EIS)
:
Issuance of Lead Agency Record of Decision (Agency Action)
- Completed Date: 07/03/2023 -
Endangered Species Act Consultation (NOAA-NMFS)
:
ESA Consultation Concludes (Agency Action)
- Completed Date: 03/13/2023 -
Endangered Species Act Consultation (DOI-FWS)
:
ESA Consultation Concludes (Agency Action)
- Completed Date: 04/03/2023 -
Section 106 Review
:
Section 106 consultation concluded (Agency Action)
- Completed Date: 05/26/2023 -
Magnuson-Stevens Fishery Conservation and Management Act, Section 305 Essential Fish Habitat (EFH) Consultation
:
NOAA Issues any EFH Conservation Recommendations (Agency Action)
- Completed Date: 02/24/2023
The target is scheduled 90 days after BOEM's target date for Issuance of a Record of Decision. However, this date will be subject to dependencies, including but not limited to conclusion of consultations pursuant to Section 106 of the National Historic Preservation Act, Section 7 of the Endangered Species Act, and the Magnuson-Stevens Fishery Conservation and Management Act. It also requires receipt of the Section 408 permission, Section 401 Water Quality Certification or waiver and Coastal Zone Management Consistency determination. Note, should the BOEM ROD decision change, the Corps permit decision date would be adjusted accordingly to allow for the full 90 day review period.
Finally, the district may require a mitigation plan compliant with the Corps/EPA 2008 Joint Mitigation Rule and information regarding alternatives from the project sponsor prior to rendering a permit decision. Should submission of any required information be delayed, the district reserves its right to adjust this Target Completion Date as necessary.
Update: The final decision date was changed to Oct 5, 2023 to align with the updated BOEM schedule and BOEM ROD date of July 7, 2023.
-
Environmental Impact Statement (EIS)
:
Issuance of Lead Agency Record of Decision (Agency Action)
- Completed Date: 07/03/2023 -
Endangered Species Act Consultation (NOAA-NMFS)
:
ESA Consultation Concludes (Agency Action)
- Completed Date: 03/13/2023 -
Endangered Species Act Consultation (DOI-FWS)
:
ESA Consultation Concludes (Agency Action)
- Completed Date: 04/03/2023 -
Section 106 Review
:
Section 106 consultation concluded (Agency Action)
- Completed Date: 05/26/2023 -
Magnuson-Stevens Fishery Conservation and Management Act, Section 305 Essential Fish Habitat (EFH) Consultation
:
NOAA Issues any EFH Conservation Recommendations (Agency Action)
- Completed Date: 02/24/2023
The target is scheduled 90 days after BOEM's target date for Issuance of a Record of Decision. However, this date will be subject to dependencies, including but not limited to conclusion of consultations pursuant to Section 106 of the National Historic Preservation Act, Section 7 of the Endangered Species Act, and the Magnuson-Stevens Fishery Conservation and Management Act. It also requires receipt of the Section 408 permission, Section 401 Water Quality Certification or waiver and Coastal Zone Management Consistency determination. Note, should the BOEM ROD decision change, the Corps permit decision date would be adjusted accordingly to allow for the full 90 day review period.
Finally, the district may require a mitigation plan compliant with the Corps/EPA 2008 Joint Mitigation Rule and information regarding alternatives from the project sponsor prior to rendering a permit decision. Should submission of any required information be delayed, the district reserves its right to adjust this Target Completion Date as necessary.
Update: The final decision date was changed to Oct 5, 2023 to align with the updated BOEM schedule and BOEM ROD date of July 7, 2023.
PROJECT WEBSITE: Ocean Wind
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
SUBJECT TO CHANGE
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Renewable Energy Production
CATEGORY
Project Category
FAST-41 Covered Projects
LEAD AGENCY
Department of the Interior, Bureau of Ocean Energy Management
View FAST-41 Postings by Agencies
Other Agencies with Actions or Authorizations:
Department of the Army, US Army Corps of Engineers - Regulatory
Department of Commerce, National Oceanic and Atmospheric Administration
Department of the Interior, Fish and Wildlife Service
Environmental Protection Agency
Department of the Army, US Army Corps of Engineers - Civil Works
Description:
Ocean Wind, LLC intends to construct, operate and maintain a commercial-scale offshore wind energy facility located approximately 15 miles off the coast of New Jersey within Lease Area OCS-A 0498 (the “Ocean Wind 1 Project”). The Ocean Wind 1 Project, consisting of up to 98 wind turbine generators (WTG), inter-array cables, up to three Offshore Substations (OSS), two onshore substations, and two transmission cable routes making landfall in Ocean County, New Jersey and Cape May County, New Jersey, is intended to fulfill the New Jersey Board of Public Utilities’ (BPU) September 20, 2018, solicitation for 1,100 MW of offshore wind capacity, and a corresponding Offshore Wind Renewable Energy Certificate (OREC) allowance of 4,851,489 MW-hours per year was awarded to Ocean Wind via BPU on June 21, 2019 (BPU Docket No. QO18121289, In the Matter of the Board of Public Utilities Offshore Wind Solicitation for 1,100 MW – Evaluation of the Offshore Wind Applications). The Ocean Wind 1 Project would contribute to New Jersey’s goal of 7.5 gigawatts (GW) of offshore wind energy generation by 2035 as outlined in New Jersey Governor’s Executive Order No. 92, issued on November 19, 2019.
Update:
The Executive Director granted a Bureau of Ocean Energy Management (BOEM) request to extend the Endangered Species Act Consultation completion date on September 23, 2022. The Executive Director determination is posted here.
The Executive Director granted a Bureau of Ocean Energy Management (BOEM) request to extend the EFH consultation and Endangered Species Act Consultation completion date on November 18, 2022. The Executive Director determination is posted here.
The Executive Director granted a Bureau of Ocean Energy Management (BOEM) request to extend the Endangered Species Act Consultation completion date on December 16, 2022. The Executive Director determination is posted here.
The Executive Director granted a Bureau of Ocean Energy Management (BOEM) request to extend the Construction and Operations Plan, Environmental Impact Statement, and Section 106 completion date on January 31, 2023. The Executive Director determination is posted here.
-
Environmental Impact Statement (EIS)
:
Issuance of Lead Agency Record of Decision (Agency Action)
- Completed Date: 07/03/2023 -
Endangered Species Act Consultation (NOAA-NMFS)
:
ESA Consultation Concludes (Agency Action)
- Completed Date: 03/13/2023 -
Endangered Species Act Consultation (DOI-FWS)
:
ESA Consultation Concludes (Agency Action)
- Completed Date: 04/03/2023 -
Section 106 Review
:
Section 106 consultation concluded (Agency Action)
- Completed Date: 05/26/2023 -
Magnuson-Stevens Fishery Conservation and Management Act, Section 305 Essential Fish Habitat (EFH) Consultation
:
NOAA Issues any EFH Conservation Recommendations (Agency Action)
- Completed Date: 02/24/2023
The target is scheduled 90 days after BOEM's target date for Issuance of a Record of Decision. However, this date will be subject to dependencies, including but not limited to conclusion of consultations pursuant to Section 106 of the National Historic Preservation Act, Section 7 of the Endangered Species Act, and the Magnuson-Stevens Fishery Conservation and Management Act. It also requires receipt of the Section 408 permission, Section 401 Water Quality Certification or waiver and Coastal Zone Management Consistency determination. Note, should the BOEM ROD decision change, the Corps permit decision date would be adjusted accordingly to allow for the full 90 day review period.
Finally, the district may require a mitigation plan compliant with the Corps/EPA 2008 Joint Mitigation Rule and information regarding alternatives from the project sponsor prior to rendering a permit decision. Should submission of any required information be delayed, the district reserves its right to adjust this Target Completion Date as necessary.
-
Environmental Impact Statement (EIS)
:
Issuance of Lead Agency Record of Decision (Agency Action)
- Completed Date: 07/03/2023 -
Endangered Species Act Consultation (NOAA-NMFS)
:
ESA Consultation Concludes (Agency Action)
- Completed Date: 03/13/2023 -
Endangered Species Act Consultation (DOI-FWS)
:
ESA Consultation Concludes (Agency Action)
- Completed Date: 04/03/2023 -
Section 106 Review
:
Section 106 consultation concluded (Agency Action)
- Completed Date: 05/26/2023 -
Magnuson-Stevens Fishery Conservation and Management Act, Section 305 Essential Fish Habitat (EFH) Consultation
:
NOAA Issues any EFH Conservation Recommendations (Agency Action)
- Completed Date: 02/24/2023
The target is scheduled 90 days after BOEM's target date for Issuance of a Record of Decision. However, this date will be subject to dependencies, including but not limited to conclusion of consultations pursuant to Section 106 of the National Historic Preservation Act, Section 7 of the Endangered Species Act, and the Magnuson-Stevens Fishery Conservation and Management Act. It also requires receipt of the Section 408 permission, Section 401 Water Quality Certification or waiver and Coastal Zone Management Consistency determination. Note, should the BOEM ROD decision change, the Corps permit decision date would be adjusted accordingly to allow for the full 90 day review period.
Finally, the district may require a mitigation plan compliant with the Corps/EPA 2008 Joint Mitigation Rule and information regarding alternatives from the project sponsor prior to rendering a permit decision. Should submission of any required information be delayed, the district reserves its right to adjust this Target Completion Date as necessary.
Update: The final decision date was changed to Oct 5, 2023 to align with the updated BOEM schedule and BOEM ROD date of July 7, 2023.
Original Target Date: 07/13/2023
Milestone: Final Verification/Permit Decision Rendered (Agency Action)
Requested extensions greater than 30 days for this Action are shown below:
Final Verification/Permit Decision Rendered (Agency Action) extended by 84
From: 07/13/2023
To: 10/05/2023