USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Permitting Action Modification History

Complete
USACE completed the milestone ahead of schedule, on 10/3/23.
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 04-27-2022 04-27-2022 --- Yes
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 05-11-2022 05-11-2022 --- Yes
Publication of Public Notice (Agency Action) 06-24-2022 06-17-2022 --- Yes
Final Verification/Permit Decision Rendered (Agency Action) 07-13-2023 10-03-2023 --- Yes
In Progress
The milestone was changed in accordance with BOEM's updated schedule.
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 04-27-2022 04-27-2022 --- Yes
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 05-11-2022 05-11-2022 --- Yes
Publication of Public Notice (Agency Action) 06-24-2022 06-17-2022 --- Yes
Final Verification/Permit Decision Rendered (Agency Action) 07-13-2023 10-05-2023 --- No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 04-27-2022 04-27-2022 --- Yes
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 05-11-2022 05-11-2022 --- Yes
Publication of Public Notice (Agency Action) 06-24-2022 06-17-2022 --- Yes
Final Verification/Permit Decision Rendered (Agency Action) 07-13-2023 07-13-2023 --- No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 04-27-2022 04-27-2022 --- Yes
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 05-11-2022 05-11-2022 --- Yes
Publication of Public Notice (Agency Action) 06-24-2022 06-24-2022 --- No
Final Verification/Permit Decision Rendered (Agency Action) 07-13-2023 07-13-2023 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) --- 04-27-2022 --- Yes
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) --- 05-11-2022 --- No
Publication of Public Notice (Agency Action) --- 06-24-2022 --- No
Final Verification/Permit Decision Rendered (Agency Action) --- 07-13-2023 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) --- 04-27-2022 --- No
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) --- 05-11-2022 --- No
Publication of Public Notice (Agency Action) --- 06-24-2022 --- No
Final Verification/Permit Decision Rendered (Agency Action) --- 07-13-2023 --- No