The Target Completion date is being changed as per overall changes in BOEM's schedule. The Corps' milestone is dependent on the BOEM ROD date, which also changed.
Cooperating under NEPA
Description:
Department of Army authorization from the US Army Corps of Engineers Norfolk District is required pursuant to Section 10 of the Rivers and Harbors Act of 1899 (RHA) and Section 404 of the Clean Water Act. Activities that require authorization include: installation of the cable from 3 nm to the high tide line and any onshore discharges of fill into jurisdictional waters, including wetlands.
Milestones:
The project sponsor on April 6, 2021 has indicated they are agreeable to submitting the initial permit application 30 days prior to BOEM's anticipated issuance of the draft EIS, which would be September 1, 2022.
Update: due to changes in BOEM's schedule, the new initial permit application date was moved from Feb 22, 2023 to Dec 27, 2023.
Update: due to changes in BOEM's schedule, the new initial permit application date was moved to Mar 27, 2024.
The Corps anticipates working closely with the sponsor to ensure the initial application contains all the
items needed for a complete application. It is anticipated that any completeness items needed after the
initial submittal will be received within 15 days of the initial submittal.
Schedule updated as per changes in BOEM's overall schedule.
A public notice will be issued to coincide with BOEM's target date for publication of the Official Notice of
Availability of a draft EIS in the Federal Register so long as the Corps has received a complete
application by that date.
-
Environmental Impact Statement (EIS)
:
Issuance of Lead Agency Record of Decision (Agency Action)
- Current Target Date: 05/18/2026 -
Endangered Species Act Consultation (NOAA-NMFS)
:
ESA Consultation Concludes (Agency Action)
- Current Target Date: 11/27/2023 -
Section 106 Review
:
Section 106 consultation concluded (Agency Action)
- Current Target Date: 05/18/2026 -
Section 408 Permit
:
Issuance of Decision (Agency Action)
- Current Target Date: 09/15/2026 -
Endangered Species Act Consultation (DOI-FWS)
:
ESA Consultation Concludes (Agency Action)
- Current Target Date: 06/12/2023 -
Magnuson-Stevens Fishery Conservation and Management Act, Section 305 Essential Fish Habitat (EFH) Consultation
:
NOAA Issues any EFH Conservation Recommendations (Agency Action)
- Current Target Date: 08/28/2023
The Corps anticipates making a permit decision 120 days after BOEM's Issuance of a Record of Decision (ROD). Should BOEM's ROD target date slip, the permit decision date will also change on a day by day basis to allow for full 90 day decision making period. However, this date will be subject to dependencies, including but not limited to conclusion of consultations pursuant to Section 106 of the National Historic Preservation Act, Section 7 of the Endangered Species Act, and the Magnuson-Stevens Fishery Conservation and Management Act. It also requires receipt of the Section 408 permission, Section 401 Water Quality Certification or waiver and Coastal Zone Management Consistency determination.
Finally, the district may require a mitigation plan compliant with the Corps/EPA 2008 Joint Mitigation Rule and information regarding alternatives from the project sponsor prior to rendering a permit decision. Should submission of any required information be delayed, the district reserves its right to adjust this Target Completion Date as necessary.
-
Environmental Impact Statement (EIS)
:
Issuance of Lead Agency Record of Decision (Agency Action)
- Current Target Date: 05/18/2026 -
Endangered Species Act Consultation (NOAA-NMFS)
:
ESA Consultation Concludes (Agency Action)
- Current Target Date: 11/27/2023 -
Section 106 Review
:
Section 106 consultation concluded (Agency Action)
- Current Target Date: 05/18/2026 -
Section 408 Permit
:
Issuance of Decision (Agency Action)
- Current Target Date: 09/15/2026 -
Endangered Species Act Consultation (DOI-FWS)
:
ESA Consultation Concludes (Agency Action)
- Current Target Date: 06/12/2023 -
Magnuson-Stevens Fishery Conservation and Management Act, Section 305 Essential Fish Habitat (EFH) Consultation
:
NOAA Issues any EFH Conservation Recommendations (Agency Action)
- Current Target Date: 08/28/2023
The Corps anticipates making a permit decision 120 days after BOEM's Issuance of a Record of Decision (ROD). Should BOEM's ROD target date slip, the permit decision date will also change on a day by day basis to allow for full 90 day decision making period. However, this date will be subject to dependencies, including but not limited to conclusion of consultations pursuant to Section 106 of the National Historic Preservation Act, Section 7 of the Endangered Species Act, and the Magnuson-Stevens Fishery Conservation and Management Act. It also requires receipt of the Section 408 permission, Section 401 Water Quality Certification or waiver and Coastal Zone Management Consistency determination.
Finally, the district may require a mitigation plan compliant with the Corps/EPA 2008 Joint Mitigation Rule and information regarding alternatives from the project sponsor prior to rendering a permit decision. Should submission of any required information be delayed, the district reserves its right to adjust this Target Completion Date as necessary.
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Renewable Energy Production
CATEGORY
Project Category
FAST-41 Covered Projects
LEAD AGENCY
Department of the Interior, Bureau of Ocean Energy Management
View FAST-41 Postings by Agencies
Description:
Update: In June 2022, the project name changed from Kitty Hawk Wind Project to Kitty Hawk North Wind Project to reflect the segmenting of the project.
The purpose of the Kitty Hawk North Wind Project is to develop a commercial-scale, offshore wind energy facility in Commercial Lease OCS-A 0508 offshore North Carolina, with up to 69 total wind turbine generators, 1 offshore substation (also called “electrical service platform”), inter-array cables, 1 onshore substation, and up to 2 transmission cables making landfall in Virginia Beach, Virginia, and connecting to the Pennsylvania-New Jersey-Maryland (PJM) Interconnection energy grid. Kitty Hawk is actively seeking one or more power purchase agreement awards for this project. The project is intended to substantially contribute to the region’s electrical reliability and help Virginia achieve its renewable energy goals as stated in the Virginia Clean Economy Act.
FAST-41 provides increased transparency and predictability by requiring Federal agencies to publish comprehensive permitting timetables for all "covered" projects, and provides clear procedures for modifying permitting timetables to address the unpredictability inherent in the environmental review and permitting process for significant infrastructure projects. For more information, see "The FAST-41 Process" at https://www.permits.performance.gov/fpisc-content/fast-41-process.
-
Environmental Impact Statement (EIS)
:
Issuance of Lead Agency Record of Decision (Agency Action)
- Current Target Date: 05/18/2026 -
Endangered Species Act Consultation (NOAA-NMFS)
:
ESA Consultation Concludes (Agency Action)
- Current Target Date: 11/27/2023 -
Section 106 Review
:
Section 106 consultation concluded (Agency Action)
- Current Target Date: 05/18/2026 -
Section 408 Permit
:
Issuance of Decision (Agency Action)
- Current Target Date: 09/15/2026 -
Endangered Species Act Consultation (DOI-FWS)
:
ESA Consultation Concludes (Agency Action)
- Current Target Date: 06/12/2023 -
Magnuson-Stevens Fishery Conservation and Management Act, Section 305 Essential Fish Habitat (EFH) Consultation
:
NOAA Issues any EFH Conservation Recommendations (Agency Action)
- Current Target Date: 08/28/2023
The Corps anticipates making a permit decision 90 days after BOEM's Issuance of a Record of Decision (ROD). Should BOEM's ROD target date slip, the permit decision date will also change on a day by day basis to allow for full 120 day decision making period. However, this date will be subject to dependencies, including but not limited to conclusion of consultations pursuant to Section 106 of the National Historic Preservation Act, Section 7 of the Endangered Species Act, and the Magnuson-Stevens Fishery Conservation and Management Act. It also requires receipt of the Section 408 permission, Section 401 Water Quality Certification or waiver and Coastal Zone Management Consistency determination.
Finally, the district may require a mitigation plan compliant with the Corps/EPA 2008 Joint Mitigation Rule and information regarding alternatives from the project sponsor prior to rendering a permit decision. Should submission of any required information be delayed, the district reserves its right to adjust this Target Completion Date as necessary.
-
Environmental Impact Statement (EIS)
:
Issuance of Lead Agency Record of Decision (Agency Action)
- Current Target Date: 05/18/2026 -
Endangered Species Act Consultation (NOAA-NMFS)
:
ESA Consultation Concludes (Agency Action)
- Current Target Date: 11/27/2023 -
Section 106 Review
:
Section 106 consultation concluded (Agency Action)
- Current Target Date: 05/18/2026 -
Section 408 Permit
:
Issuance of Decision (Agency Action)
- Current Target Date: 09/15/2026 -
Endangered Species Act Consultation (DOI-FWS)
:
ESA Consultation Concludes (Agency Action)
- Current Target Date: 06/12/2023 -
Magnuson-Stevens Fishery Conservation and Management Act, Section 305 Essential Fish Habitat (EFH) Consultation
:
NOAA Issues any EFH Conservation Recommendations (Agency Action)
- Current Target Date: 08/28/2023
The Corps anticipates making a permit decision 120 days after BOEM's Issuance of a Record of Decision (ROD). Should BOEM's ROD target date slip, the permit decision date will also change on a day by day basis to allow for full 90 day decision making period. However, this date will be subject to dependencies, including but not limited to conclusion of consultations pursuant to Section 106 of the National Historic Preservation Act, Section 7 of the Endangered Species Act, and the Magnuson-Stevens Fishery Conservation and Management Act. It also requires receipt of the Section 408 permission, Section 401 Water Quality Certification or waiver and Coastal Zone Management Consistency determination.
Finally, the district may require a mitigation plan compliant with the Corps/EPA 2008 Joint Mitigation Rule and information regarding alternatives from the project sponsor prior to rendering a permit decision. Should submission of any required information be delayed, the district reserves its right to adjust this Target Completion Date as necessary.
Original Target Date: 11/01/2023
Milestone: Final Verification/Permit Decision Rendered (Agency Action)
Requested extensions greater than 30 days for this Action are shown below:
Final Verification/Permit Decision Rendered (Agency Action) extended by 608
From: 04/28/2024
To: 07/01/2025