Permitting Action Modification History

Cancelled
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 09-01-2022 06-11-2025 --- No
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 09-15-2022 06-26-2025 --- No
Publication of Public Notice (Agency Action) 09-30-2022 07-11-2025 --- No
Final Verification/Permit Decision Rendered (Agency Action) 11-01-2023 09-15-2026 --- No
Planned
The changes to the PDE as described above will need to be analyzed and considered by USACE as part of their permitting processes. In addition, the Section 10/404 final completion date is dependent upon the final completion date of BOEM’s NEPA action. For this project, the USACE review will require 120 days between issuance of the ROD and issuance of USACE’s Section 10/404 decision. Therefore, an extension of the Section 10/404 final completion date is requested based upon the extension of the NEPA completion date.
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 09-01-2022 06-11-2025 --- No
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 09-15-2022 06-26-2025 --- No
Publication of Public Notice (Agency Action) 09-30-2022 07-11-2025 --- No
Final Verification/Permit Decision Rendered (Agency Action) 11-01-2023 09-15-2026 --- No
Planned
The Corps milestone changed in accordance with the overall BOEM schedule adjustments.
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 09-01-2022 03-27-2024 --- No
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 09-15-2022 04-11-2024 --- No
Publication of Public Notice (Agency Action) 09-30-2022 04-26-2024 --- No
Final Verification/Permit Decision Rendered (Agency Action) 11-01-2023 07-01-2025 --- No
Planned
The project proponent will be submitting their permit application at a later time, as part of an overall schedule shift stemming from the timing of the initial MMPA permit application submission.
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 09-01-2022 02-22-2023 --- No
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 09-15-2022 03-09-2023 --- No
Publication of Public Notice (Agency Action) 09-30-2022 03-24-2023 --- No
Final Verification/Permit Decision Rendered (Agency Action) 11-01-2023 04-28-2024 --- No