Milestone Extension: Section 10 Rivers and Harbors Act of 1899 and Section 404 Clean Water Act

Submitted by craig.litteken… on

The Section 10/404 milestones are dependent on BOEM’s EIS action milestones. A shift of BOEM’s EIS action milestones by 417 days results in a commensurate shift to the Section 10/404 action milestones.  Therefore, an extension of the Section 10/404 milestones is requested based upon the extension of BOEM’s COP and EIS milestones.

Action
Project Name: Responsible Agency:
US Army Corps of Engineers - Regulatory
Agency Status: Cooperating under FAST-41
Cooperating under NEPA
Status:
Planned
POC Name:
Naomi Handell, Regulatory Program Manager
POC Title:
Sec 10/404 FAST-41 Dashboard Administrator

Milestones:

Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action)
Current Target Date:
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action)
Current Target Date:
Publication of Public Notice (Agency Action)
Current Target Date:
Final Verification/Permit Decision Rendered (Agency Action)
Current Target Date:
Milestone
Final Verification/Permit Decision Rendered (Agency Action)
Current Target Date:
Project

PROJECT WEBSITE: Skipjack Wind

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING

0 out of 0

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Renewable Energy Production

SECTOR
Renewable Energy Production

Project Category

CATEGORY
Project Category FAST-41 Covered Projects

Department of the Interior

LEAD AGENCY
Department of the Interior, Bureau of Ocean Energy Management

View FAST-41 Postings by Agencies

Description:

Skipjack Offshore Energy, LLC (SJOE) intends to develop, build, operate, and own (through one or more affiliated special purpose entities) an offshore wind farm located approximately 15 miles off the coast of Delaware within Lease Areas OCS A0519 and OCS A0482. The purpose of the Project is to construct and operate a new offshore wind farm designed to help one or more states within the mid-Atlantic region meet their clean energy goals. The Project would consist of up to 72 wind turbine generators (“WTG”), associated inter-array cabling, new onshore and offshore substations, transmission cables and onshore works for connection to the wholesale electric grid administered by PJM Interconnection L.L.C.

 

The Executive Director granted a Bureau of Ocean Energy Management request to extend completion dates for all actions on March 24, 2025. The Executive Director determination is posted here.

field_status
System Comments
Furthest out
Original Target Date: 11/09/2027
Milestone: Final Verification/Permit Decision Rendered (Agency Action)

Requested extensions greater than 30 days for this Action are shown below:

Final Verification/Permit Decision Rendered (Agency Action) extended by 300
From: 07/12/2028
To: 09/04/2028
Approver Comments
BOEM submitted an Executive Director Determination Request to update the project schedule, but since that time, the project sponsor has withdrawn the project from FAST-41. Therefore, the milestone extension request is not needed and is rejected.
Missed Date Process
No
Missed Date Triggered by Extension
No
Original Milestone
Final Verification/Permit Decision Rendered (Agency Action)
Current Target Date:
Furthest Original Target Date Milestone
Final Verification/Permit Decision Rendered (Agency Action)
Current Target Date: