USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Permitting Action Modification History

Planned
BOEM is requesting these completion date modifications due to the timing of the Project Sponsor’s submission of a revised Construction and Operations Plan (COP) containing additional data and assessments that BOEM requires prior to issuing a Notice of Intent (NOI) to prepare an Environmental Impact Statement (EIS) under NEPA. BOEM has requested that the revised COP contain certain survey data for one of the proposed cable routes as well as the following assessments: the Navigational Safety Risk Assessment; Historic Resources Visual Effects Assessment for certain facilities; Marine Archaeological Resource Assessment for a particular cable route; and the Terrestrial Archeological Resource Assessment for all routes and facilities in the onshore project design envelope. The Project Sponsor intends to submit the revised COP containing all the requested information on October 27, 2025.  The Section 10/404 final completion date is dependent upon the final completion date of BOEM’s NEPA action. USACE requests a review of 90 days between issuance of the ROD and issuance of USACE’s decisions.
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 06-22-2026 03-22-2027 --- No
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 08-06-2026 05-06-2027 --- No
Publication of Public Notice (Agency Action) 08-21-2026 05-21-2027 --- No
Final Verification/Permit Decision Rendered (Agency Action) 11-09-2027 07-12-2028 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 06-22-2026 06-22-2026 --- No
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 08-06-2026 08-06-2026 --- No
Publication of Public Notice (Agency Action) 08-21-2026 08-21-2026 --- No
Final Verification/Permit Decision Rendered (Agency Action) 11-09-2027 11-09-2027 --- No