Permitting Action Modification History

Complete
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 04-10-2024 04-10-2024 --- Yes
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 04-10-2024 04-10-2024 --- Yes
Final Verification/Permit Decision Rendered (Agency Action) 06-10-2024 08-08-2024 --- Yes
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 04-10-2024 04-10-2024 --- Yes
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 04-10-2024 04-10-2024 --- Yes
Final Verification/Permit Decision Rendered (Agency Action) 06-10-2024 08-08-2024 --- No
Planned
The completion date for USACE’s Section 10/404 permit decision is dependent on the completion date for the NEPA action and is being extended to be concurrent with finalization of the EA. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 04-10-2024 04-10-2024 --- No
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 04-10-2024 04-10-2024 --- No
Final Verification/Permit Decision Rendered (Agency Action) 06-10-2024 08-08-2024 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 04-10-2024 04-10-2024 --- No
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 04-10-2024 04-10-2024 --- No
Final Verification/Permit Decision Rendered (Agency Action) 06-10-2024 06-10-2024 --- No