USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Permitting Action Modification History

Complete
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 04-10-2024 04-10-2024 --- Yes
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 04-10-2024 04-10-2024 --- Yes
Final Verification/Permit Decision Rendered (Agency Action) 06-10-2024 08-08-2024 --- Yes
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 04-10-2024 04-10-2024 --- Yes
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 04-10-2024 04-10-2024 --- Yes
Final Verification/Permit Decision Rendered (Agency Action) 06-10-2024 08-08-2024 --- No
Planned
The completion date for USACE’s Section 10/404 permit decision is dependent on the completion date for the NEPA action and is being extended to be concurrent with finalization of the EA.
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 04-10-2024 04-10-2024 --- No
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 04-10-2024 04-10-2024 --- No
Final Verification/Permit Decision Rendered (Agency Action) 06-10-2024 08-08-2024 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 04-10-2024 04-10-2024 --- No
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 04-10-2024 04-10-2024 --- No
Final Verification/Permit Decision Rendered (Agency Action) 06-10-2024 06-10-2024 --- No