USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Portions of this site may be affected due to a lapse in appropriations and associated shutdown/furloughs. Please monitor this page for updates on site availability and operating status.

Milestone Extension: Right-of-Way Authorization (DOI-BLM)

Submitted by jennifer.malla… on

Project bonding is needed to issue the notice to proceed. BLM contacted the project sponsor and was not able to get a timeframe in which bonding is expected to be completed. BLM is moving the milestone 6 months to account for the unknown timeframe the sponsor will need to bond the project. This was discussed with FPISC staff on 1/14/22.

Action
Project Name: Responsible Agency:
Bureau of Land Management
Status:
In Progress
POC Name:
Lane Cowger
POC Title:
Project Manager
POC Email:
Public Participation Website:

Description:

BLM is responding to an application for a right-of-way on public lands for (description of facility). If the BLM offers a right-of-way grant to the applicant, the target date for this action will be the offer date of the right-of-way grant to the applicant for their signature.

Milestones:

Initial application received (Agency Action)
Completed Date:
Completed application received (Agency Action)
Completed Date:
Final decision/agency action (Agency Action)
Completed Date:
Avian Protection Plan (Applicant Action)
Completed Date:
Project

PROJECT WEBSITE: Ten West Link Transmission Project

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
07/13/2022

5 out of 5

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Electricity Transmission

SECTOR
Electricity Transmission

Project Category

CATEGORY
Project Category FAST-41 Covered Projects

Department of the Interior

LEAD AGENCY
Department of the Interior, Bureau of Land Management

Other Agencies with Actions or Authorizations:

Department of the Interior

Department of the Interior, Fish and Wildlife Service

Department of Transportation

Department of Transportation, Federal Aviation Administration

Description:

DCR Transmission, LLC (DCRT) filed a right-of-way (ROW) application (SF-299) with the Bureau of Land Management (BLM) on September 14, 2014, that proposes to construct, operate, maintain, and decommission an electric transmission project in western Arizona and eastern California. The proposed Ten West Link 500 kilovolt (kV) Transmission Line Project (the Project) would consist of a 500kV transmission line traversing approximately 114 miles. The Project would increase transmission capacity by 3,200 megawatts (MW) and provide interconnection capability for new energy projects located near the Project.

The Project would begin at the Arizona Public Service Company (APS) Delaney Substation near Tonopah, Arizona, and terminate at the Southern California Edison (SCE) Colorado River Substation near Blythe, California. The Project would be located in Maricopa and La Paz counties in Arizona, and Riverside County in California.

field_status
System Comments
Furthest out
Original Target Date: 08/04/2021
Milestone: Avian Protection Plan

Requested extensions greater than 30 days for this Action are shown below:

Notice to proceed extended by 376
From: 02/15/2022
To: 08/15/2022
Missed Date Process
No
Missed Date Triggered by Extension
No
Furthest Original Target Date Milestone
Avian Protection Plan (Applicant Action)
Completed Date: