Permitting Action Modification History

Complete
Updated date as part of generic milestone / action outcome revision. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application received (Agency Action) 09-14-2015 09-14-2015 --- Yes
Completed application received (Agency Action) 01-25-2016 01-25-2016 --- Yes
Final decision/agency action (Agency Action) 09-30-2018 07-13-2022 --- Yes
Complete
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application received (Agency Action) 09-14-2015 09-14-2015 --- Yes
Completed application received (Agency Action) 01-25-2016 01-25-2016 --- Yes
Final decision/agency action (Agency Action) 09-30-2018 02-21-2020 --- Yes
Complete
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application received (Agency Action) 09-14-2015 09-14-2015 --- Yes
Completed application received (Agency Action) 01-25-2016 01-25-2016 --- Yes
Final decision/agency action (Agency Action) 09-30-2018 02-21-2020 --- Yes
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application received (Agency Action) 09-14-2015 09-14-2015 --- Yes
Completed application received (Agency Action) 01-25-2016 01-25-2016 --- Yes
Final decision/agency action (Agency Action) 09-30-2018 02-21-2020 --- Yes
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application received (Agency Action) 09-14-2015 09-14-2015 --- Yes
Completed application received (Agency Action) 01-25-2016 01-25-2016 --- Yes
Final decision/agency action (Agency Action) 09-30-2018 02-21-2020 --- Yes
Avian Protection Plan (Applicant Action) 08-04-2021 08-04-2021 --- Yes