The completion date for the OSC Air Permit follows BOEM’s ROD issuance. This enables EPA to ensure compliance with ESA and other federal statutes, while meeting substantive requirements of the Clean Air Act.
Cooperating under NEPA
Description:
The EPA promulgated the Outer Continental Shelf (OCS) air regulations (40 CFR part 55) pursuant to Section 328 of the Clean Air Act (CAA). OCS permits contain various requirements including preconstruction permit requirements under the New Source Review (NSR) permitting program and operating permit requirements under the Title V permitting program. OCS permits also include New Source Performance Standards (NSPS), National Emissions Standards for Hazardous Air Pollutants (NESHAPS) and/or state and local air pollution control requirements for sources locating within 25 miles of a state’s seaward boundary (the line 3 nautical miles distant from a state’s coastline (9 nautical miles for Texas and Florida)). OCS permit issuance is a federal action that triggers EPA obligations under other federal statutes (e.g., National Historic Preservation Act (NHPA), Endangered Species Act (ESA), Magnuson-Stevens Fishery Conservation and Management Act (MSA)). The Bureau of Ocean and Energy Management (BOEM) is the lead Federal agency for ensuring compliance with ESA, MSA and NHPA. EPA is a co-action agency for all ESA, MSA and NHPA compliance activities associated with wind development projects on the Atlantic OCS. OCS permits are issued by EPA regional offices or delegated state and local permitting authorities. To date, the EPA has delegated the OCS permitting program to three states (Delaware, Maryland and Virginia) and four permitting authorities in California (San Luis Obispo County Air Pollution Control District (APCD), Santa Barbara County APCD, South Coast Air Quality Management District and Ventura County APCD).
Once an OCS permit application is determined complete by the applicable permitting authority, the permitting authority develops and issues a draft OCS permit. This draft OCS permit is open for public comment, usually for a 30-day public comment period, and after comments are evaluated, a response to comments document is developed. Public notice documents can be found on the applicable permitting authority website.
Although EPA’s OCS air permitting projects are not subject to the National Environmental Policy Act (NEPA), the EPA actively participates in BOEM's processes under NEPA for each of the OCS projects off the Atlantic coast and considers BOEM’s environmental analyses, including the NEPA Record of Decision (ROD), in the development of the OCS air permit for each source. The ROD explains BOEM’s decision under NEPA, the alternatives BOEM considered and BOEM’s plans for mitigation and monitoring, if necessary. EPA’s final permit decision occurs after the issuance of the ROD, which fulfills EPA’s statutory obligations under ESA, MSA and NHPA. The final permit must be issued no later than one year from the date EPA determines that the OCS permit application is complete. OCS permit application submission and review milestones are discussed in more detail below.
Milestones:
The OCS permit application process begins when a project sponsor determines that a proposed activity is likely to require an OCS permit and, after initial consultation, notifies EPA of its intent to file an application (if the project is within 25 miles of the state’s seaward boundary). Per the OCS permitting implementing regulations at 40 CFR Part 55, the Notice of Intent (NOI) target date is no earlier than 18 months before a permit application is submitted. For FAST-41 purposes, EPA projects this milestone and all subsequent project milestones ahead of the receipt of the NOI and works with the permit applicant to refine these milestones as the project moves through the OCS permitting process.
The permit application must demonstrate compliance with all applicable requirements before it is submitted to the air permitting authority. Those requirements are stated in 40 CFR Part 55, which include but are not limited to, New Source Review (NSR) permitting, title V permitting, New Source Performance Standards (NSPS), National Emissions Standards for Hazardous Air Pollutants (NESHAPs) and any applicable state and local requirements.
Ahead of this milestone, EPA and the project developer conduct pre-application meetings as necessary to identify data and information needs, applicable OCS permitting requirements (e.g., air pollution control requirements, air quality modeling requirements) and policy issues for the proposed project. It is recommended that preapplication meetings start to occur 9 months ahead of this milestone’s target date. The air quality modeling protocol required as part of the permit application submittal is recommended to be sent to the permitting authority 6 months prior to this milestone.
In accordance with 40 CFR 124.3(c), EPA notifies the permit applicant whether the permit application is complete or incomplete within 30 days after receiving such application. If incomplete, EPA will ask the permit applicant to submit any additional information necessary to make the permit application complete.
Once the permit application addresses all EPA requirements, EPA will send a letter in writing to the permit applicant confirming that the permit application is complete. The milestone will be checked (on the dashboard) when completeness is confirmed.
-
Monthly Status Report for January 2025:EPA's final OCS air permit decision under Section 328 of the Clean Air Act is dependent on the BOEM’s Record of Decision (ROD) for the project. EPA generally estimates final permit issuance will occur 90 days after BOEM’s ROD issuance and anticipates making this decision by the alternative completion date currently reflected on the dashboard of February 25, 2025.
-
Monthly Status Report for December 2024:EPA's final OCS air permit decision under Section 328 of the Clean Air Act is dependent on the BOEM’s Record of Decision (ROD) for the project. EPA generally estimates final permit issuance will occur 90 days after BOEM’s ROD issuance and anticipates making this decision by the alternative completion date currently reflected on the dashboard of February 25, 2025.
-
Monthly Status Report for November 2024:EPA's final OCS air permit decision under Section 328 of the Clean Air Act is dependent on the BOEM’s Record of Decision (ROD) for the project. EPA generally estimates final permit issuance will occur 90 days after BOEM’s ROD issuance and anticipates making this decision by the alternative completion date currently reflected on the dashboard of February 25, 2025.
-
Monthly Status Report for October 2024:EPA's final OCS air permit decision under Section 328 of the Clean Air Act is dependent on the BOEM’s Record of Decision (ROD) for the project. EPA generally estimates final permit issuance will occur 90 days after BOEM’s ROD issuance and anticipates making this decision by the alternative completion date currently reflected on the dashboard of February 25, 2025.
-
Monthly Status Report for September 2024:EPA's final OCS air permit decision under Section 328 of the Clean Air Act is dependent on the BOEM’s Record of Decision (ROD) for the project. EPA generally estimates final permit issuance will occur 90 days after BOEM’s ROD issuance and anticipates making this decision by the alternative completion date currently reflected on the dashboard of February 25, 2025.
-
Monthly Status Report for August 2024:EPA's final OCS air permit decision under Section 328 of the Clean Air Act is dependent on the BOEM’s Record of Decision (ROD) for the project. EPA generally estimates final permit issuance will occur 90 days after BOEM’s ROD issuance and anticipates making this decision by the alternative completion date currently reflected on the dashboard of February 25, 2025.
-
Monthly Status Report for July 2024:EPA's final OCS air permit decision under Section 328 of the Clean Air Act is dependent on the BOEM’s Record of Decision (ROD) for the project. EPA generally estimates final permit issuance will occur 90 days after BOEM’s ROD issuance and anticipates making this decision by the alternative completion date currently reflected on the dashboard of February 25, 2025.
-
Monthly Status Report for June 2024:EPA's final OCS air permit decision under Section 328 of the Clean Air Act is dependent on the BOEM’s Record of Decision (ROD) for the project. EPA generally estimates final permit issuance will occur 90 days after BOEM’s ROD issuance and anticipates making this decision by the alternative completion date currently reflected on the dashboard of February 25, 2025.
-
Monthly Status Report for May 2024:EPA's final OCS air permit decision under Section 328 of the Clean Air Act is dependent on the BOEM’s Record of Decision (ROD) for the project. EPA generally estimates final permit issuance will occur 90 days after BOEM’s ROD issuance and anticipates making this decision by the alternative completion date currently reflected on the dashboard of February 25, 2025.
-
Non-conformance Explanation:The Environmental Protection Agency's (EPA’s) Outer Continental Shelf (OCS) permit decision under Section 328 of the Clean Air Act is dependent upon the Bureau of Ocean and Energy Management's (BOEM’s) completion of the NEPA Record of Decision (ROD). EPA projected the need for a minimum of 90 days after issuance of the ROD to review the ROD and verify that associated documents address requirements EPA must meet under statutes other than the Clean Air Act (CAA). BOEM undertook a comprehensive review of the permitting timetable for SouthCoast Wind with the cooperating agencies and in consultation with the Project Sponsor. The review encompassed all remaining milestone dates for the project, including this one. Based on that review, in December of 2023, BOEM initiated development of a revised permitting timetable. BOEM and EPA subsequently participated in three convening meetings with the Permitting Council and the Project Sponsor. Furthermore, on February 16, 2024, BOEM, on behalf of EPA, timely submitted a request to the Permitting Council Executive Director (Executive Director) to extend the final completion dates for EPA's OCS air permit decision. However, the Executive Director did not sign a determination on the record granting the request by the statutory deadline of March 8, 2024 (30 days prior to the posted OCS air permit completion date of April 8, 2024) due to the uncertainty surrounding the schedule, specifically the final ROD date. Therefore, EPA could not modify the permitting timetable to reflect the extended completion date. BOEM provided a revised permitting timetable before the Permitting Council to reset the schedule for the remaining milestones on 4/8/2024 and EPA appropriately established an alternative completion date for SouthCoast's OCS air permit decision of February 25, 2025.
The target date for this milestone is one year after the date EPA determines that the OCS air permit application is complete. This milestone also reflects timely receipt of BOEM’s Record of Decision (ROD) for the project, which must occur prior to issuance of a final permit. EPA generally estimates final permit issuance will occur 90 days after BOEM’s ROD issuance.
-
Monthly Status Report for January 2025:EPA's final OCS air permit decision under Section 328 of the Clean Air Act is dependent on the BOEM’s Record of Decision (ROD) for the project. EPA generally estimates final permit issuance will occur 90 days after BOEM’s ROD issuance and anticipates making this decision by the alternative completion date currently reflected on the dashboard of February 25, 2025.
-
Monthly Status Report for December 2024:EPA's final OCS air permit decision under Section 328 of the Clean Air Act is dependent on the BOEM’s Record of Decision (ROD) for the project. EPA generally estimates final permit issuance will occur 90 days after BOEM’s ROD issuance and anticipates making this decision by the alternative completion date currently reflected on the dashboard of February 25, 2025.
-
Monthly Status Report for November 2024:EPA's final OCS air permit decision under Section 328 of the Clean Air Act is dependent on the BOEM’s Record of Decision (ROD) for the project. EPA generally estimates final permit issuance will occur 90 days after BOEM’s ROD issuance and anticipates making this decision by the alternative completion date currently reflected on the dashboard of February 25, 2025.
-
Monthly Status Report for October 2024:EPA's final OCS air permit decision under Section 328 of the Clean Air Act is dependent on the BOEM’s Record of Decision (ROD) for the project. EPA generally estimates final permit issuance will occur 90 days after BOEM’s ROD issuance and anticipates making this decision by the alternative completion date currently reflected on the dashboard of February 25, 2025.
-
Monthly Status Report for September 2024:EPA's final OCS air permit decision under Section 328 of the Clean Air Act is dependent on the BOEM’s Record of Decision (ROD) for the project. EPA generally estimates final permit issuance will occur 90 days after BOEM’s ROD issuance and anticipates making this decision by the alternative completion date currently reflected on the dashboard of February 25, 2025.
-
Monthly Status Report for August 2024:EPA's final OCS air permit decision under Section 328 of the Clean Air Act is dependent on the BOEM’s Record of Decision (ROD) for the project. EPA generally estimates final permit issuance will occur 90 days after BOEM’s ROD issuance and anticipates making this decision by the alternative completion date currently reflected on the dashboard of February 25, 2025.
-
Monthly Status Report for July 2024:EPA's final OCS air permit decision under Section 328 of the Clean Air Act is dependent on the BOEM’s Record of Decision (ROD) for the project. EPA generally estimates final permit issuance will occur 90 days after BOEM’s ROD issuance and anticipates making this decision by the alternative completion date currently reflected on the dashboard of February 25, 2025.
-
Monthly Status Report for June 2024:EPA's final OCS air permit decision under Section 328 of the Clean Air Act is dependent on the BOEM’s Record of Decision (ROD) for the project. EPA generally estimates final permit issuance will occur 90 days after BOEM’s ROD issuance and anticipates making this decision by the alternative completion date currently reflected on the dashboard of February 25, 2025.
-
Monthly Status Report for May 2024:EPA's final OCS air permit decision under Section 328 of the Clean Air Act is dependent on the BOEM’s Record of Decision (ROD) for the project. EPA generally estimates final permit issuance will occur 90 days after BOEM’s ROD issuance and anticipates making this decision by the alternative completion date currently reflected on the dashboard of February 25, 2025.
-
Non-conformance Explanation:The Environmental Protection Agency's (EPA’s) Outer Continental Shelf (OCS) permit decision under Section 328 of the Clean Air Act is dependent upon the Bureau of Ocean and Energy Management's (BOEM’s) completion of the NEPA Record of Decision (ROD). EPA projected the need for a minimum of 90 days after issuance of the ROD to review the ROD and verify that associated documents address requirements EPA must meet under statutes other than the Clean Air Act (CAA). BOEM undertook a comprehensive review of the permitting timetable for SouthCoast Wind with the cooperating agencies and in consultation with the Project Sponsor. The review encompassed all remaining milestone dates for the project, including this one. Based on that review, in December of 2023, BOEM initiated development of a revised permitting timetable. BOEM and EPA subsequently participated in three convening meetings with the Permitting Council and the Project Sponsor. Furthermore, on February 16, 2024, BOEM, on behalf of EPA, timely submitted a request to the Permitting Council Executive Director (Executive Director) to extend the final completion dates for EPA's OCS air permit decision. However, the Executive Director did not sign a determination on the record granting the request by the statutory deadline of March 8, 2024 (30 days prior to the posted OCS air permit completion date of April 8, 2024) due to the uncertainty surrounding the schedule, specifically the final ROD date. Therefore, EPA could not modify the permitting timetable to reflect the extended completion date. BOEM provided a revised permitting timetable before the Permitting Council to reset the schedule for the remaining milestones on 4/8/2024 and EPA appropriately established an alternative completion date for SouthCoast's OCS air permit decision of February 25, 2025.
The target date for this milestone is one year after the date EPA determines that the OCS air permit application is complete. This milestone also reflects timely receipt of BOEM’s Record of Decision (ROD) for the project, which must occur prior to issuance of a final permit. EPA generally estimates final permit issuance will occur 90 days after BOEM’s ROD issuance.
PROJECT WEBSITE: https://southcoastwind.com/
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
10/30/2026
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Renewable Energy Production
CATEGORY
Project Category
FAST-41 Covered Projects
LEAD AGENCY
Department of the Interior, Bureau of Ocean Energy Management
View FAST-41 Postings by Agencies
Description:
Updated February 2023: Mayflower Wind Project name changed to SouthCoast Wind Project.
The purpose of the SouthCoast Wind Project is to provide clean, renewable wind energy to the Northeast United States, including to Massachusetts. SouthCoast Wind will support reliability in Massachusetts and in the New England region, while meeting the Commonwealth’s statutory need for renewable/clean energy. The SouthCoast Wind Project also supports the federal need of grid reliability, as set forth the Federal Power Act in Section 215. Out of the 6.7 million people living in Massachusetts, nearly 5.1 million people live along coastal areas of the state. Offshore wind projects like SouthCoast Wind can provide a localized energy source to coastal populations.
The Executive Director granted a Bureau of Ocean Energy Management request to extend the OCS Air Permit completion date on November 30, 2023. The Executive Director determination is posted here.
-
Monthly Status Report for January 2025:EPA's final OCS air permit decision under Section 328 of the Clean Air Act is dependent on the BOEM’s Record of Decision (ROD) for the project. EPA generally estimates final permit issuance will occur 90 days after BOEM’s ROD issuance and anticipates making this decision by the alternative completion date currently reflected on the dashboard of February 25, 2025.
-
Monthly Status Report for December 2024:EPA's final OCS air permit decision under Section 328 of the Clean Air Act is dependent on the BOEM’s Record of Decision (ROD) for the project. EPA generally estimates final permit issuance will occur 90 days after BOEM’s ROD issuance and anticipates making this decision by the alternative completion date currently reflected on the dashboard of February 25, 2025.
-
Monthly Status Report for November 2024:EPA's final OCS air permit decision under Section 328 of the Clean Air Act is dependent on the BOEM’s Record of Decision (ROD) for the project. EPA generally estimates final permit issuance will occur 90 days after BOEM’s ROD issuance and anticipates making this decision by the alternative completion date currently reflected on the dashboard of February 25, 2025.
-
Monthly Status Report for October 2024:EPA's final OCS air permit decision under Section 328 of the Clean Air Act is dependent on the BOEM’s Record of Decision (ROD) for the project. EPA generally estimates final permit issuance will occur 90 days after BOEM’s ROD issuance and anticipates making this decision by the alternative completion date currently reflected on the dashboard of February 25, 2025.
-
Monthly Status Report for September 2024:EPA's final OCS air permit decision under Section 328 of the Clean Air Act is dependent on the BOEM’s Record of Decision (ROD) for the project. EPA generally estimates final permit issuance will occur 90 days after BOEM’s ROD issuance and anticipates making this decision by the alternative completion date currently reflected on the dashboard of February 25, 2025.
-
Monthly Status Report for August 2024:EPA's final OCS air permit decision under Section 328 of the Clean Air Act is dependent on the BOEM’s Record of Decision (ROD) for the project. EPA generally estimates final permit issuance will occur 90 days after BOEM’s ROD issuance and anticipates making this decision by the alternative completion date currently reflected on the dashboard of February 25, 2025.
-
Monthly Status Report for July 2024:EPA's final OCS air permit decision under Section 328 of the Clean Air Act is dependent on the BOEM’s Record of Decision (ROD) for the project. EPA generally estimates final permit issuance will occur 90 days after BOEM’s ROD issuance and anticipates making this decision by the alternative completion date currently reflected on the dashboard of February 25, 2025.
-
Monthly Status Report for June 2024:EPA's final OCS air permit decision under Section 328 of the Clean Air Act is dependent on the BOEM’s Record of Decision (ROD) for the project. EPA generally estimates final permit issuance will occur 90 days after BOEM’s ROD issuance and anticipates making this decision by the alternative completion date currently reflected on the dashboard of February 25, 2025.
-
Monthly Status Report for May 2024:EPA's final OCS air permit decision under Section 328 of the Clean Air Act is dependent on the BOEM’s Record of Decision (ROD) for the project. EPA generally estimates final permit issuance will occur 90 days after BOEM’s ROD issuance and anticipates making this decision by the alternative completion date currently reflected on the dashboard of February 25, 2025.
-
Non-conformance Explanation:The Environmental Protection Agency's (EPA’s) Outer Continental Shelf (OCS) permit decision under Section 328 of the Clean Air Act is dependent upon the Bureau of Ocean and Energy Management's (BOEM’s) completion of the NEPA Record of Decision (ROD). EPA projected the need for a minimum of 90 days after issuance of the ROD to review the ROD and verify that associated documents address requirements EPA must meet under statutes other than the Clean Air Act (CAA). BOEM undertook a comprehensive review of the permitting timetable for SouthCoast Wind with the cooperating agencies and in consultation with the Project Sponsor. The review encompassed all remaining milestone dates for the project, including this one. Based on that review, in December of 2023, BOEM initiated development of a revised permitting timetable. BOEM and EPA subsequently participated in three convening meetings with the Permitting Council and the Project Sponsor. Furthermore, on February 16, 2024, BOEM, on behalf of EPA, timely submitted a request to the Permitting Council Executive Director (Executive Director) to extend the final completion dates for EPA's OCS air permit decision. However, the Executive Director did not sign a determination on the record granting the request by the statutory deadline of March 8, 2024 (30 days prior to the posted OCS air permit completion date of April 8, 2024) due to the uncertainty surrounding the schedule, specifically the final ROD date. Therefore, EPA could not modify the permitting timetable to reflect the extended completion date. BOEM provided a revised permitting timetable before the Permitting Council to reset the schedule for the remaining milestones on 4/8/2024 and EPA appropriately established an alternative completion date for SouthCoast's OCS air permit decision of February 25, 2025.
The target date for this milestone is one year after the date EPA determines that the OCS air permit application is complete. This milestone also reflects timely receipt of BOEM’s Record of Decision (ROD) for the project, which must occur prior to issuance of a final permit. EPA generally estimates final permit issuance will occur 90 days after BOEM’s ROD issuance.
-
Monthly Status Report for January 2025:EPA's final OCS air permit decision under Section 328 of the Clean Air Act is dependent on the BOEM’s Record of Decision (ROD) for the project. EPA generally estimates final permit issuance will occur 90 days after BOEM’s ROD issuance and anticipates making this decision by the alternative completion date currently reflected on the dashboard of February 25, 2025.
-
Monthly Status Report for December 2024:EPA's final OCS air permit decision under Section 328 of the Clean Air Act is dependent on the BOEM’s Record of Decision (ROD) for the project. EPA generally estimates final permit issuance will occur 90 days after BOEM’s ROD issuance and anticipates making this decision by the alternative completion date currently reflected on the dashboard of February 25, 2025.
-
Monthly Status Report for November 2024:EPA's final OCS air permit decision under Section 328 of the Clean Air Act is dependent on the BOEM’s Record of Decision (ROD) for the project. EPA generally estimates final permit issuance will occur 90 days after BOEM’s ROD issuance and anticipates making this decision by the alternative completion date currently reflected on the dashboard of February 25, 2025.
-
Monthly Status Report for October 2024:EPA's final OCS air permit decision under Section 328 of the Clean Air Act is dependent on the BOEM’s Record of Decision (ROD) for the project. EPA generally estimates final permit issuance will occur 90 days after BOEM’s ROD issuance and anticipates making this decision by the alternative completion date currently reflected on the dashboard of February 25, 2025.
-
Monthly Status Report for September 2024:EPA's final OCS air permit decision under Section 328 of the Clean Air Act is dependent on the BOEM’s Record of Decision (ROD) for the project. EPA generally estimates final permit issuance will occur 90 days after BOEM’s ROD issuance and anticipates making this decision by the alternative completion date currently reflected on the dashboard of February 25, 2025.
-
Monthly Status Report for August 2024:EPA's final OCS air permit decision under Section 328 of the Clean Air Act is dependent on the BOEM’s Record of Decision (ROD) for the project. EPA generally estimates final permit issuance will occur 90 days after BOEM’s ROD issuance and anticipates making this decision by the alternative completion date currently reflected on the dashboard of February 25, 2025.
-
Monthly Status Report for July 2024:EPA's final OCS air permit decision under Section 328 of the Clean Air Act is dependent on the BOEM’s Record of Decision (ROD) for the project. EPA generally estimates final permit issuance will occur 90 days after BOEM’s ROD issuance and anticipates making this decision by the alternative completion date currently reflected on the dashboard of February 25, 2025.
-
Monthly Status Report for June 2024:EPA's final OCS air permit decision under Section 328 of the Clean Air Act is dependent on the BOEM’s Record of Decision (ROD) for the project. EPA generally estimates final permit issuance will occur 90 days after BOEM’s ROD issuance and anticipates making this decision by the alternative completion date currently reflected on the dashboard of February 25, 2025.
-
Monthly Status Report for May 2024:EPA's final OCS air permit decision under Section 328 of the Clean Air Act is dependent on the BOEM’s Record of Decision (ROD) for the project. EPA generally estimates final permit issuance will occur 90 days after BOEM’s ROD issuance and anticipates making this decision by the alternative completion date currently reflected on the dashboard of February 25, 2025.
-
Non-conformance Explanation:The Environmental Protection Agency's (EPA’s) Outer Continental Shelf (OCS) permit decision under Section 328 of the Clean Air Act is dependent upon the Bureau of Ocean and Energy Management's (BOEM’s) completion of the NEPA Record of Decision (ROD). EPA projected the need for a minimum of 90 days after issuance of the ROD to review the ROD and verify that associated documents address requirements EPA must meet under statutes other than the Clean Air Act (CAA). BOEM undertook a comprehensive review of the permitting timetable for SouthCoast Wind with the cooperating agencies and in consultation with the Project Sponsor. The review encompassed all remaining milestone dates for the project, including this one. Based on that review, in December of 2023, BOEM initiated development of a revised permitting timetable. BOEM and EPA subsequently participated in three convening meetings with the Permitting Council and the Project Sponsor. Furthermore, on February 16, 2024, BOEM, on behalf of EPA, timely submitted a request to the Permitting Council Executive Director (Executive Director) to extend the final completion dates for EPA's OCS air permit decision. However, the Executive Director did not sign a determination on the record granting the request by the statutory deadline of March 8, 2024 (30 days prior to the posted OCS air permit completion date of April 8, 2024) due to the uncertainty surrounding the schedule, specifically the final ROD date. Therefore, EPA could not modify the permitting timetable to reflect the extended completion date. BOEM provided a revised permitting timetable before the Permitting Council to reset the schedule for the remaining milestones on 4/8/2024 and EPA appropriately established an alternative completion date for SouthCoast's OCS air permit decision of February 25, 2025.
The target date for this milestone is one year after the date EPA determines that the OCS air permit application is complete. This milestone also reflects timely receipt of BOEM’s Record of Decision (ROD) for the project, which must occur prior to issuance of a final permit. EPA generally estimates final permit issuance will occur 90 days after BOEM’s ROD issuance.
Original Target Date: 01/25/2024
Milestone: Issuance of final decision/permit approval (Agency Action)
Requested extensions greater than 30 days for this Action are shown below:
Issuance of final decision/permit approval (Agency Action) extended by 397
From: 04/08/2024
To: 02/25/2025