USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Permitting Action Modification History

Complete
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
NOI to apply for an Air Permit submitted (Applicant Action) 05-31-2022 05-31-2022 --- Yes
OCS Air Permit application submitted (Applicant Action) 10-26-2022 11-23-2022 --- Yes
OCS Air Permit application complete (Applicant Action) 01-25-2023 04-07-2023 --- Yes
Issuance of final decision/permit approval (Agency Action) 01-25-2024 04-08-2024 01-17-2025 Yes
In Progress
The completion date for the OSC Air Permit follows BOEM’s ROD issuance. This enables EPA to ensure compliance with ESA and other federal statutes, while meeting substantive requirements of the Clean Air Act.
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
NOI to apply for an Air Permit submitted (Applicant Action) 05-31-2022 05-31-2022 --- Yes
OCS Air Permit application submitted (Applicant Action) 10-26-2022 11-23-2022 --- Yes
OCS Air Permit application complete (Applicant Action) 01-25-2023 04-07-2023 --- Yes
Issuance of final decision/permit approval (Agency Action) 01-25-2024 04-08-2024 02-25-2025 No
In Progress
The requested date accounts for a one-year statutory deadline that the Clean Air Act gives EPA to reach an OCS air permitting decision following EPA’s determination that a project sponsor has submitted a complete application. EPA deemed the Project Sponsor’s OCS air permit application complete on April 7, 2023.
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
NOI to apply for an Air Permit submitted (Applicant Action) 05-31-2022 05-31-2022 --- Yes
OCS Air Permit application submitted (Applicant Action) 10-26-2022 11-23-2022 --- Yes
OCS Air Permit application complete (Applicant Action) 01-25-2023 04-07-2023 --- Yes
Issuance of final decision/permit approval (Agency Action) 01-25-2024 04-08-2024 --- No
In Progress
EPA provided comments to Southcoast requesting additional analysis and clarifications on their OCS air permit. Due to these deficiencies, proposed to Southcoast a new application complete date of April 13, 2023 was set. SouthCoast application was deemed complete on April 7, 2023.
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
NOI to apply for an Air Permit submitted (Applicant Action) 05-31-2022 05-31-2022 --- Yes
OCS Air Permit application submitted (Applicant Action) 10-26-2022 11-23-2022 --- Yes
OCS Air Permit application complete (Applicant Action) 01-25-2023 04-07-2023 --- Yes
Issuance of final decision/permit approval (Agency Action) 01-25-2024 01-25-2024 --- No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
NOI to apply for an Air Permit submitted (Applicant Action) 05-31-2022 05-31-2022 --- Yes
OCS Air Permit application submitted (Applicant Action) 10-26-2022 11-23-2022 --- Yes
OCS Air Permit application complete (Applicant Action) 01-25-2023 04-13-2023 --- Yes
Issuance of final decision/permit approval (Agency Action) 01-25-2024 01-25-2024 --- No
Planned
EPA provided comments to Southcoast requesting additional analysis and clarifications on their OCS air permit. Due to these deficiencies, proposed to Southcoast a new application complete date of April 13, 2023. That enables Southcoast time to address the comments and EPA time to review the revisions. 
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
NOI to apply for an Air Permit submitted (Applicant Action) 05-31-2022 05-31-2022 --- Yes
OCS Air Permit application submitted (Applicant Action) 10-26-2022 11-23-2022 --- Yes
OCS Air Permit application complete (Applicant Action) 01-25-2023 04-13-2023 --- No
Issuance of final decision/permit approval (Agency Action) 01-25-2024 01-25-2024 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
NOI to apply for an Air Permit submitted (Applicant Action) 05-31-2022 05-31-2022 --- Yes
OCS Air Permit application submitted (Applicant Action) 10-26-2022 11-23-2022 --- Yes
OCS Air Permit application complete (Applicant Action) 01-25-2023 02-28-2023 --- No
Issuance of final decision/permit approval (Agency Action) 01-25-2024 01-25-2024 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
NOI to apply for an Air Permit submitted (Applicant Action) 05-31-2022 05-31-2022 --- Yes
OCS Air Permit application submitted (Applicant Action) 10-26-2022 11-23-2022 --- No
OCS Air Permit application complete (Applicant Action) 01-25-2023 02-28-2023 --- No
Issuance of final decision/permit approval (Agency Action) 01-25-2024 01-25-2024 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
NOI to apply for an Air Permit submitted (Applicant Action) 05-31-2022 05-31-2022 --- Yes
OCS Air Permit application submitted (Applicant Action) 10-26-2022 10-26-2022 --- No
OCS Air Permit application complete (Applicant Action) 01-25-2023 01-25-2023 --- No
Issuance of final decision/permit approval (Agency Action) 01-25-2024 01-25-2024 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
NOI to apply for an Air Permit submitted (Applicant Action) --- 05-31-2022 --- No
OCS Air Permit application submitted (Applicant Action) --- 10-26-2022 --- No
OCS Air Permit application complete (Applicant Action) --- 01-25-2023 --- No
Issuance of final decision/permit approval (Agency Action) --- 01-25-2024 --- No