USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Permitting Action Modification History

Planned
The new schedule accommodates the timing of offshore surveys and the submission of additional information needed for the NEPA process and environmental permitting.
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
NOI to apply for an Air Permit submitted (Applicant Action) 12-29-2023 02-13-2026 --- No
OCS Air Permit application submitted (Applicant Action) 10-01-2024 09-15-2026 --- No
OCS Air Permit application complete (Applicant Action) 12-30-2024 03-15-2027 --- No
Issuance of final decision/permit approval (Agency Action) 12-30-2025 03-15-2028 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
NOI to apply for an Air Permit submitted (Applicant Action) 12-29-2023 12-29-2023 --- No
OCS Air Permit application submitted (Applicant Action) 10-01-2024 10-01-2024 --- No
OCS Air Permit application complete (Applicant Action) 12-30-2024 12-30-2024 --- No
Issuance of final decision/permit approval (Agency Action) 12-30-2025 12-30-2025 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
NOI to apply for an Air Permit submitted (Applicant Action) --- 12-29-2023 --- No
OCS Air Permit application submitted (Applicant Action) --- 10-01-2024 --- No
OCS Air Permit application complete (Applicant Action) --- 12-30-2024 --- No
Issuance of final decision/permit approval (Agency Action) --- 12-30-2025 --- No