Milestone Extension: Operations Plan / Surface Use Plan

Submitted by giannina.dimai… on

Due to issues identified in the Section 106 Review, the FEIS and ROD need to be moved to allow for further Section 106 consultation, which in turn also moves out the BLM Plan of Operations final authorization date.

Action
Project Name: Responsible Agency:
Bureau of Land Management
Status:
In Progress
POC Name:
Ronald Nuckles
POC Title:
Field Manager
POC Email:

Milestones:

Initial application submitted (Applicant Action)
Completed Date:
Application deemed complete (Agency Action)
Completed Date:
Final decision/agency action (Agency Action)
Current Target Date:
Milestone
Final decision/agency action (Agency Action)
Current Target Date:
Project

PROJECT WEBSITE: Castle Mountain Mine Phase 2 Project

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
04/30/2027

0 out of 8

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Mining

SECTOR
Mining

Project Category

CATEGORY
Project Category FAST-41 Covered Projects

Department of the Interior

LEAD AGENCY
Department of the Interior, Bureau of Land Management

View FAST-41 Postings by Agencies

Other Agencies with Actions or Authorizations:

Department of the Interior

Department of the Interior, Fish and Wildlife Service

Department of the Army

Department of the Army, US Army Corps of Engineers - Regulatory

Description:

Castle Mountain Mine is a permitted and operating gold and silver open pit and heap leach mine located in San Bernardino County, California.  The Project proposes to continue mining at an increased rate within the existing Bureau of Land Management approved mine plan boundary, extending the mining schedule by approximately 20 years. 

The Castle Mountain Mine Phase 2 Project proposes to expand an open-pit gold mine in the eastern Mojave Desert of California, approximately 60 miles south of Las Vegas, Nevada and 40 miles northwest of the Bureau of Land Management California Desert District's Needles Field Office. The mine is the second largest active gold mine in the state of California and has proven potential to produce over four million ounces of gold. This is the BLM's first mining project to receive full coverage under FAST-41. The project qualifies for coverage based on: 1) estimated reserves of over four million ounces of gold: 2) >$2M initial capital investment; and 3) >$4B in capital and operating expenses over the life of the project.

The project consists of the mine's expansion over a 20-year period and construction of a multi-state water pipeline and powerline. Operations would effectively quadruple the annual mining rate from 18 million tons to 80 million tons. The increased rate would require 2,250 acre-feet per year of groundwater and up to 25 megawatts of power. To help meet these demands, Castle Mountain Venture would construct a 32-mile water pipeline and a 16.5-mile powerline. The expansion of the mine pits, overburden sites, heap leach pad, and installation of the utilities would disturb an additional 1,810 acres of BLM-managed land, for a total project disturbance of 3,287 acres.

The Executive Director granted a Bureau of Land Management request to extend the Environmental Impact Statement, Section 106 of the National Historic Preservation Act review, Plan of Operations, and Right-of-Way Authorization completion dates on July 27, 2026. The Executive Director determination is posted here.

The Executive Director granted a Bureau of Land Management request to extend the Environmental Impact Statement, Section 106 of the National Historic Preservation Act review, Plan of Operations, and Right-of-Way Authorization completion dates on October 9, 2026. The Executive Director determination is posted here.

field_status
System Comments
Furthest out
Original Target Date: 10/15/2026
Milestone: Final decision/agency action (Agency Action)

Requested extensions greater than 30 days for this Action are shown below:

Final decision/agency action (Agency Action) extended by 134
From: 12/30/2026
To: 02/26/2027
Approver Comments
On 10/09/26, the Permitting Council Executive Director granted BLM's request to modify the Project's permitting timetable pursuant to 42 U.S.C. § 4370m-2(c)(2)(D)(i)(IV).
Missed Date Process
No
Missed Date Triggered by Extension
No
Original Milestone
Final decision/agency action (Agency Action)
Current Target Date:
Furthest Original Target Date Milestone
Final decision/agency action (Agency Action)
Current Target Date: