Permitting Action Modification History
Modifications on 10/09/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Initial application submitted (Applicant Action) | 03-01-2022 | 03-01-2022 | --- | Yes |
| Application deemed complete (Agency Action) | 10-10-2025 | 10-10-2025 | --- | Yes |
| Final decision/agency action (Agency Action) | 10-15-2026 | 02-26-2027 | --- | No |
Modifications on 07/27/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Initial application submitted (Applicant Action) | 03-01-2022 | 03-01-2022 | --- | Yes |
| Application deemed complete (Agency Action) | 10-10-2025 | 10-10-2025 | --- | Yes |
| Final decision/agency action (Agency Action) | 10-15-2026 | 12-30-2026 | --- | No |
Modifications on 10/10/2025
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Initial application submitted (Applicant Action) | 03-01-2022 | 03-01-2022 | --- | Yes |
| Application deemed complete (Agency Action) | 10-10-2025 | 10-10-2025 | --- | Yes |
| Final decision/agency action (Agency Action) | 10-15-2026 | 10-15-2026 | --- | No |
Modifications on 08/08/2025
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Initial application submitted (Applicant Action) | 03-01-2022 | 03-01-2022 | --- | Yes |
| Application deemed complete (Agency Action) | 10-10-2025 | 10-10-2025 | --- | No |
| Final decision/agency action (Agency Action) | 10-15-2026 | 10-15-2026 | --- | No |