Permitting Action Modification History

Complete
The project sponsor submitted the required financial assurance information ahead of time., basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial Mine Plan of Operations received (Applicant Action) 11-19-2020 11-19-2020 --- Yes
Completeness determination for Mine Plan of Operations (Agency Action) 12-01-2020 12-01-2020 --- Yes
Issuance of decision for Mine Plan of Operations (Agency Action) 05-15-2026 06-15-2026 --- Yes
Financial assurance received (Applicant Action) 05-15-2026 06-26-2026 --- Yes
In Progress
This milestone was completed earlier than the original proposed date due to internal agency factors., basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial Mine Plan of Operations received (Applicant Action) 11-19-2020 11-19-2020 --- Yes
Completeness determination for Mine Plan of Operations (Agency Action) 12-01-2020 12-01-2020 --- Yes
Issuance of decision for Mine Plan of Operations (Agency Action) 05-15-2026 06-15-2026 --- Yes
Financial assurance received (Applicant Action) 05-15-2026 06-30-2026 --- No
In Progress
The explanation for the milestone date change is outlined in the Executive Director Determination posted on the project page. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial Mine Plan of Operations received (Applicant Action) 11-19-2020 11-19-2020 --- Yes
Completeness determination for Mine Plan of Operations (Agency Action) 12-01-2020 12-01-2020 --- Yes
Issuance of decision for Mine Plan of Operations (Agency Action) 05-15-2026 06-22-2026 --- No
Financial assurance received (Applicant Action) 05-15-2026 06-30-2026 --- No
In Progress
The milestones were changed in error and are being moved back to the original target dates. Any future date change will require consultation as required under FAST-41. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial Mine Plan of Operations received (Applicant Action) 11-19-2020 11-19-2020 --- Yes
Completeness determination for Mine Plan of Operations (Agency Action) 12-01-2020 12-01-2020 --- Yes
Issuance of decision for Mine Plan of Operations (Agency Action) 05-15-2026 05-15-2026 --- No
Financial assurance received (Applicant Action) 05-15-2026 05-15-2026 --- No
In Progress
To align with NRC , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial Mine Plan of Operations received (Applicant Action) 11-19-2020 11-19-2020 --- Yes
Completeness determination for Mine Plan of Operations (Agency Action) 12-01-2020 12-01-2020 --- Yes
Issuance of decision for Mine Plan of Operations (Agency Action) 05-15-2026 05-29-2026 --- No
Financial assurance received (Applicant Action) 05-15-2026 06-15-2026 --- No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial Mine Plan of Operations received (Applicant Action) 11-19-2020 11-19-2020 --- Yes
Completeness determination for Mine Plan of Operations (Agency Action) 12-01-2020 12-01-2020 --- Yes
Issuance of decision for Mine Plan of Operations (Agency Action) 05-15-2026 05-15-2026 --- No
Financial assurance received (Applicant Action) 05-15-2026 05-15-2026 --- No