1. BLM and NRC
2. BLM has communicated with the project sponsor. Also, to align with NRC milestones
Cooperating under NEPA
Milestones:
PROJECT WEBSITE: https://deweyburdock.info/
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
05/29/2026
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Mining
CATEGORY
Project Category
FAST-41 Covered Projects
LEAD AGENCY
Nuclear Regulatory Commission
View FAST-41 Postings by Agencies
Other Agencies with Actions or Authorizations:
Department of the Interior, Bureau of Land Management
Description:
The Dewey Burdock In-Situ Recovery (ISR) Uranium Project is a proposed uranium production facility located in Fall River and Custer Counties, South Dakota. The project will recover uranium from subsurface sandstone ore bodies through ISR technology, which involves the injection of a lixiviant solution into production wellfields to dissolve uranium minerals in place and pump the uranium-bearing solution to a central processing plant for recovery. The use of ISR technology allows for minimal surface disturbance compared to conventional open-pit or underground uranium mining. The project consists of wellfield areas, a central processing plant, supporting infrastructure and environmental protection systems. The project has been licensed by the NRC (Source Material License SUA-1600) and is progressing toward final state and federal authorizations required to begin commercial production.
During that coordination, the IPA indicated this change to the EA milestone was acceptable, though the shift from 5/15/26 to 6/15/26 is 31 days, not 30 days. The EA milestone needed to move to 5/15, not 5/14 (which would have conformed to the 30-day limit) because the 106 final milestone is 5/15/26.
Original Target Date: 05/15/2026
Milestone: Issuance of decision for Mine Plan of Operations (Agency Action)
Requested extensions greater than 30 days for this Action are shown below:
Financial assurance received (Applicant Action) extended by 31
From: 05/15/2026
To: 06/15/2026