USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Portions of this site may be affected due to a lapse in appropriations and associated shutdown/furloughs. Please monitor this page for updates on site availability and operating status.

Milestone Extension: Marine Mammal Protection Act (MMPA) Incidental Take Authorization (DOC – NOAA/NMFS)

Submitted by craig.litteken… on

The proposed rule milestone date was extended to allow for time needed for review and clearance.  The final rule milestone date was extended due to the fact that BOEM's EIS schedule was revised.  Due to the fact that the final rule can't be published prior to the ROD, the milestone date needed to be extended. 

Action
Project Name: Responsible Agency:
National Oceanic and Atmospheric Administration
Agency Status: Cooperating under FAST-41
Cooperating under NEPA
Status:
In Progress
POC Name:
Sue Tuxbury
POC Title:
Fishery Biologist/Wind Coordinator

Description:

The Marine Mammal Protection Act (MMPA) prohibits "take" of marine mammals with certain exceptions. An incidental take authorization, which may be issued provided certain findings are made, allows for the "take" of marine mammals provided the authorized entity abides by mitigation and monitoring measures and take limits established in the authorization. The project proponent has communicated to NMFS that the activity may result in the incidental “take" of marine mammals and has expressed plans to submit a request for an MMPA incidental take authorization. Based on initial feedback from the applicant, we anticipate the incidental take authorization under the MMPA for this project will be a letter of authorization.

Milestones:

ITA Application Submitted (Applicant Action)
Completed Date:
NOAA Determines ITA Application is Complete (Applicant Action)
Completed Date:
Milestone Details

This date is based on the applicant submitting an initial, draft LOA application to NMFS at least 6 months prior to ensure time for the applicant to provide additional information or make revisions that NMFS indicates are necessary in order to deem the application adequate and complete.  The date reflects 6-8 months prior to release of the proposed rule or concurrent with cooperating agency review of DEIS (whichever is earlier). 

Publish Notice of Receipt in Federal Register (LOA Only) (Agency Action)
Completed Date:
Milestone Details

This date is 30 days after receipt of an adequate and complete application. NOAA’s ability to meet this schedule is contingent upon receipt of an adequate and complete application from the applicant.

Publish Proposed ITA in Federal Register (Agency Action)
Current Target Date:
Milestone Details

This date is 6-8 months after the adequate and complete application is received, after the DEIS is released for public comment, and aligns with the schedule to complete ESA consultation.  NOAA’s ability to meet this schedule is contingent upon receipt of required information from the applicant, the extent and nature of public comments received on the Notice of Receipt, and the ability of NMFS to preliminarily make the required findings. 


Publish Final ITA Regulations in Federal Register (LOA Only) (Agency Action)
Current Target Date:
Milestone Details

This date reflects no less than six months after publishing the proposed regulations, no sooner than 60 days after the Record of Decision (ROD), and is contingent upon issuance of the Biological Opinion, FEIS and ROD. NOAA’s ability to meet this schedule is contingent upon receipt of required information from the applicant, the extent and nature of public comments received on the proposed ITA, and the ability of NMFS to make the required findings.

ITA decision rendered (Agency Action)
Current Target Date:
Milestone Details

This date reflects no less than 30 days after publishing the final regulations, and no later than 90 days following the issuance of the Record of Decision for the action.  NOAA’s ability to meet this schedule is contingent upon the issuance of the final regulations. 

Milestone
Publish Final ITA Regulations in Federal Register (LOA Only) (Agency Action)
Current Target Date:
Milestone Details

This date reflects no less than six months after publishing the proposed regulations, no sooner than 60 days after the Record of Decision (ROD), and is contingent upon issuance of the Biological Opinion, FEIS and ROD. NOAA’s ability to meet this schedule is contingent upon receipt of required information from the applicant, the extent and nature of public comments received on the proposed ITA, and the ability of NMFS to make the required findings.

Project

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
11/20/2023

9 out of 9

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Renewable Energy Production

SECTOR
Renewable Energy Production

Project Category

CATEGORY
Project Category FAST-41 Covered Projects

Department of the Interior

LEAD AGENCY
Department of the Interior, Bureau of Ocean Energy Management

View FAST-41 Postings by Agencies

Other Agencies with Actions or Authorizations:

Department of Commerce

Department of Commerce, National Oceanic and Atmospheric Administration

Department of the Army

Department of the Army, US Army Corps of Engineers - Regulatory

Environmental Protection Agency

Environmental Protection Agency

Department of the Interior

Department of the Interior, Fish and Wildlife Service

Description:

Revolution Wind LLC proposes the Revolution Wind Farm Project, an offshore wind farm to be located approximately 12 statute miles south of the coast of Rhode Island in federal waters in the area designated by the U.S. Bureau of Ocean Energy Management (BOEM) as Renewable Energy Lease Number OCS-A 0486 (the Project).

The purpose of the Project is to provide clean, reliable offshore wind energy that will increase the amount and availability of renewable energy to New England consumers while creating the opportunity to displace electricity generated by fossil fuel-powered plants and offering substantial economic and environmental benefits to the New England region. Massachusetts, Rhode Island, Connecticut, and New York have adopted substantial renewable portfolio standards and clean energy targets to address issues associated with climate change, highlighting the current and future demand for this Project.

The Project has been awarded three Power Purchase Agreements (PPAs) totaling 704 MW of generation capacity: 1) a 200 MW contract with the State of Connecticut approved in December 2018; 2) a 400 MW contract with the State of Rhode Island approved in February 2019; and 3) a 104 MW contract with the State of Connecticut approved in November 2019. The Project is being developed to fulfill its obligations to Connecticut and Rhode Island in accordance with the PPAs. The Project maximum generating capacity is 880 MW.

Update:

The Executive Director granted a Bureau of Ocean Energy Management request to extend Environmental Impact Statement, Construction and Operations Plan, and Section 106 Consultation completion dates. The Executive Director determination is posted here.

field_status
System Comments
Furthest out
Original Target Date: 08/01/2023
Milestone: ITA decision rendered (Agency Action)

Requested extensions greater than 30 days for this Action are shown below:

Publish Final ITA Regulations in Federal Register (LOA Only) (Agency Action) extended by 35
From: 08/01/2023
To: 09/05/2023
Missed Date Process
No
Missed Date Triggered by Extension
No
Original Milestone
Publish Final ITA Regulations in Federal Register (LOA Only) (Agency Action)
Current Target Date:
Milestone Details

This date reflects no less than six months after publishing the proposed regulations, no sooner than 60 days after the Record of Decision (ROD), and is contingent upon issuance of the Biological Opinion, FEIS and ROD. NOAA’s ability to meet this schedule is contingent upon receipt of required information from the applicant, the extent and nature of public comments received on the proposed ITA, and the ability of NMFS to make the required findings.

Furthest Original Target Date Milestone
ITA decision rendered (Agency Action)
Current Target Date:
Milestone Details

This date reflects no less than 30 days after publishing the final regulations, and no later than 90 days following the issuance of the Record of Decision for the action.  NOAA’s ability to meet this schedule is contingent upon the issuance of the final regulations.