Permitting Action Modification History
Modifications on 07/16/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Completed application received (Agency Action) | 09-23-2020 | 09-23-2020 | --- | Yes |
| Issuance of Preliminary Lease (Agency Action) | 02-23-2021 | 02-23-2021 | --- | Yes |
| Issuance of the Lease of Power Privilege Contract (Agency Action) | 08-20-2025 | 03-19-2027 | --- | No |
Modifications on 07/25/2025
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Completed application received (Agency Action) | 09-23-2020 | 09-23-2020 | --- | Yes |
| Issuance of Preliminary Lease (Agency Action) | 02-23-2021 | 02-23-2021 | --- | Yes |
| Issuance of the Lease of Power Privilege Contract (Agency Action) | 08-20-2025 | 01-15-2027 | --- | No |
Modifications on 09/04/2024
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Completed application received (Agency Action) | 09-23-2020 | 09-23-2020 | --- | Yes |
| Issuance of Preliminary Lease (Agency Action) | 02-23-2021 | 02-23-2021 | --- | Yes |
| Issuance of the Lease of Power Privilege Contract (Agency Action) | 08-20-2025 | 12-18-2026 | --- | No |
Modifications on 07/28/2023
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Completed application received (Agency Action) | 09-23-2020 | 09-23-2020 | --- | Yes |
| Issuance of Preliminary Lease (Agency Action) | 02-23-2021 | 02-23-2021 | --- | Yes |
| Issuance of the Lease of Power Privilege Contract (Agency Action) | 08-20-2025 | 03-18-2026 | --- | No |
Modifications on 04/03/2023
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Completed application received (Agency Action) | --- | 09-23-2020 | --- | Yes |
| Issuance of Preliminary Lease (Agency Action) | --- | 02-23-2021 | --- | Yes |
| Issuance of the Lease of Power Privilege Contract (Agency Action) | --- | 08-20-2025 | --- | No |