USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Milestone Extension: Lease of Power Privilege (DOI-BOR)

Submitted by craig.litteken… on

A detailed justification and information on consultation with the affected cooperating agencies and project sponsor are included in Commission staff’s request for Executive Director determination submitted to FPISC-OED via email.  Because the Commission’s milestone target dates, including those for issuance of the draft and final NEPA documents, are being modified to account for the additional time needed for the project sponsor to complete required studies, dependent milestone target dates are being modified accordingly.

Action
Project Name: Responsible Agency:
Bureau of Reclamation
Agency Status: Cooperating under FAST-41
Cooperating under NEPA
Status:
In Progress
POC Name:
Brad Cannon
POC Title:
Supervisory Natural Resource Specialist
POC Email:

Description:

A Lease of Power Privilege will be needed prior to any Reclamation asset being used for non-Federal power generation.

Milestones:

Completed application received (Agency Action)
Completed Date:
Issuance of Preliminary Lease (Agency Action)
Completed Date:
Issuance of the Lease of Power Privilege Contract (Agency Action)
Current Target Date:
Milestone Details

The Lease of Power Privilege is dependent on a FEIS/ROD being issued that adequately addresses Reclamation’s action.

Milestone
Issuance of the Lease of Power Privilege Contract (Agency Action)
Current Target Date:
Milestone Details

The Lease of Power Privilege is dependent on a FEIS/ROD being issued that adequately addresses Reclamation’s action.

Project

PROJECT WEBSITE: https://www.seminoepumpedstorage.com

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
12/18/2026

0 out of 7

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Renewable Energy Production

SECTOR
Renewable Energy Production

Project Category

CATEGORY
Project Category FAST-41 Covered Projects

Federal Energy Regulatory Commission

LEAD AGENCY
Federal Energy Regulatory Commission

View FAST-41 Postings by Agencies

Other Agencies with Actions or Authorizations:

Department of the Interior

Department of the Interior, Fish and Wildlife Service

Department of the Interior

Department of the Interior, Bureau of Reclamation

Department of the Army

Department of the Army, US Army Corps of Engineers - Regulatory

Department of the Interior

Department of the Interior, Bureau of Land Management

Description:

The proposed 972-megawatt project would use the Bureau of Reclamation's existing Seminoe Reservoir on the North Platte River in Carbon County, Wyoming, as a lower reservoir and include the construction of a new upper reservoir; two 30-mile-long, 500-kilovolt transmission lines; and other project facilities.  The proposed project facilities would primarily be located on Bureau of Land Management lands.

field_status
System Comments
Furthest out
Original Target Date: 08/20/2025
Milestone: Issuance of the Lease of Power Privilege Contract (Agency Action)

Requested extensions greater than 30 days for this Action are shown below:

Issuance of the Lease of Power Privilege Contract (Agency Action) extended by 210
From: 08/20/2025
To: 03/18/2026
Approver Comments
Executive Director determination signed on 7/28/23.
Missed Date Process
No
Missed Date Triggered by Extension
No
Original Milestone
Issuance of the Lease of Power Privilege Contract (Agency Action)
Current Target Date:
Milestone Details

The Lease of Power Privilege is dependent on a FEIS/ROD being issued that adequately addresses Reclamation’s action.

Furthest Original Target Date Milestone
Issuance of the Lease of Power Privilege Contract (Agency Action)
Current Target Date:
Milestone Details

The Lease of Power Privilege is dependent on a FEIS/ROD being issued that adequately addresses Reclamation’s action.