The Corps and the federal cooperating agencies, along with CPRA (the applicant), have been working diligently to prepare the Final Environmental Impact Statement (FEIS) for CPRA’s proposed Mid-Barataria Sediment Diversion (MBSD) Project. The MBSD is a large and complex project. The proposed project would discharge up to 75,000 cfs of sediment, freshwater, and nutrients within the Barataria Basin. The total cost is estimated at more than $1 billion and faces many environmental and engineering challenges due to the potential projected impacts to the Barataria Basin. In addition to the Corps’ federal actions, this EIS will be used to inform funding decisions that the Deepwater Horizon (DWH) Natural Resource Damage Assessment (NRDA) Louisiana Trustee Implementation Group (LA TIG) may make regarding restoration planning in the Barataria Basin under the Oil Pollution Act (OPA).
On March 5, 2021, the Corps, as lead federal agency for the NEPA process, released the draft EIS for 60-day public review. Public requests to extend the public review timeframe due to document length, complexity, and the regional significance of the proposed project resulted in the Corps extending the draft EIS public review period an additional 30 days. At the conclusion of the public review period, the Corps received over 43,000 comments on the draft EIS. The Corps has been working diligently with the CPRA and federal cooperating agencies to respond to public comments and advance preparation of the FEIS. During this time, southeast LA was also hit by Hurricane Ida, a category 4 storm, resulting in significant impacts to staff for the Corps, CPRA, and the federal cooperating agencies located in the region. As a result of the extended public comment period, the substantial number of public comments, and the regional impacts from Hurricane Ida, it will not be practicable for the FEIS to be completed by March 11, 2022. The Corps coordinated with the cooperating agencies and CPRA to determine a new target date for the FEIS. As lead federal agency, the Corps is requesting a 3.5-month extension to complete the FEIS (i.e. extending the March 11, 2022 FEIS target date to June 24, 2022). CPRA and the cooperating agencies concur with this new proposed target date.
The FEIS target date extension would require an extension to the target dates for the Record of Decision (ROD), FWCA, and Section 106 actions. Additionally, the information being developed for the FEIS and ROD is required for completion of the final milestones associated with the Corps 10/404 permit and 408 permission decisions. As such, the final milestone target dates associated with all of these actions will need to be extended accordingly.
The final milestones for the ROD, 404/10, 408, 106 and FWCA actions were previously scheduled to occur 30 days after the completion of the FEIS, which represents the minimum amount of time required between the completion of the FEIS and ROD in the NEPA regulations (40 CFR 1506.11(b)(2)). Given the public’s robust response to the draft EIS, the Corps, CPRA, and cooperating agencies are anticipating substantial public input on the FEIS. As such, the Corps is requesting an extension of the final target dates for the ROD, 106 action, FWCA action, 10/404 permit decision, and 408 permission from April 11, 2022 (i.e. 30 days after the FEIS) to September 22, 2022 (i.e. 90 days after the FEIS). The additional 60 days following the completion of the FEIS would allow the Corps and cooperating agencies the additional time needed to adequately assess the expected large volume of public comments on the FEIS, which is a necessary step prior to finalizing the ROD and completing the 106 process, FWCA process, and the 10/404 permit and 408 permission decisions. All the proposed changes to the permitting timetable were developed through extensive coordination with CPRA and the cooperating agencies; CPRA and the cooperating agencies concur with the proposed changes.
Description:
Two additional milestones are tracked for this project. The first is "Issuance of an updated Notice of Intent (NOI)" The milestone details is "Supplemental NOI submitted to Federal Register on April 27, 2017." The completion date is 4/27/2017. The second is "EIS Schedule/Kickoff Meeting" which has a completion date of 4/4/2017.
Milestones:
Scoping Meeting(s): Scoping meetings held on 20 July, 25 July, and 27 July 2017. Formal scoping commenting period ended on 5 September 2017.
Approximately 24 months from receipt of a revised SOW and complete/adequate information provided by CPRA
Approximately 12 months following issuance of the NOA for the Draft EIS
-
Environmental Impact Statement (EIS)
:
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action)
- Completed Date: 09/23/2022
Issuance of Record of Decision (10/404/408). 30 days after NOA for the Final EIS and completion of the Section 408 review. One ROD for all USACE decisions.
-
Environmental Impact Statement (EIS)
:
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action)
- Completed Date: 09/23/2022
Issuance of Record of Decision (10/404/408). 30 days after NOA for the Final EIS and completion of the Section 408 review. One ROD for all USACE decisions.
PROJECT WEBSITE: Mid-Barataria Sediment Diversion EIS
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
12/19/2022
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Water Resources
CATEGORY
Project Category
FAST-41 Covered Projects
LEAD AGENCY
Department of the Army, US Army Corps of Engineers - Regulatory
View FAST-41 Postings by Agencies
Other Agencies with Actions or Authorizations:
Department of Commerce, National Oceanic and Atmospheric Administration
Department of the Army, US Army Corps of Engineers - Civil Works
Department of the Interior, Fish and Wildlife Service
Description:
CURRENT STATUS:
The project status for MBSD is now "In Progress"
PROJECT DESCRIPTION:
On June 22, 2016, CPRA submitted a joint permit application which included a brief project description:
"The Mid-Barataria Sediment Diversion is a large scale, complex civil works and ecosystem restoration project. When operated, up to 75,000 cubic feet per second (cfs) of sediment laden water would be diverted from the Mississippi River to the mid-Barataria Basin to reconnect and re-establish the natural or deltaic sediment deposition process between the Mississippi River and the Barataria Basin to deliver sediment, freshwater, and nutrients to reduce land loss and sustain wetlands."
The proposed MBSD project has the potential for significant impacts and requires an Environmental Impact Statement (EIS) under the National Envrionmental Policy Act (NEPA) to inform a permit decision relative to the lead federal agency under Section 404 of the Clean Water Act (Section 404) and Section 10 of the Rivers and Harbors Act (Section 10), and permissions under Section 14 of the Rivers and Harbors Act (Section 408) The USACE-MVN Regulatory permit processing number is MVN-2012-2806-E00.
Additional project details can be found here:
Link to MBSD Regulatory webpage: here
Link to the MBSD Scoping Report (Jan 2018): here
Link to the 11 September 2017 Federal MOU for the MBSD permitting process: here
Link to the 25 January 2018 executed MOU between the State of Louisiana and FAST 41 Cooperating Agencies for the MBSD permit application: here
This Permitting Dashboard includes limitations on the types of milestones that are currently available to enter for tracking. The MBSD project involves some authorizations/laws unsupported by the Permitting Table displayed at the bottom of this webpage. For improved transparency, USACE is providing this supplemental table to track additional authorizations/laws that may be necessary for completion of the regulatory process:
| Agency | Action | Milestone Detail | Details/Status | Milestone Date |
|---|---|---|---|---|
| CPRA | Bipartisan Budget Act of 2018 | CPRA begins consultation with NMFS on marine mammal impact minimizing, monitoring, and evaluation. |
Following issuance of the MMPA waiver, the State will begin consultation with NMFS (using existing coordination processes to the extent possible) regarding practicable measures to minimize impacts to marine mammals, and measures to monitor and evaluate the impacts of the MBSD from construction, operation and maintenance. To date, the project sponsor has been in contact with NMFS about Phase I and Phase II marine mammal baseline data/monitoring. |
End Date not provided by CPRA |
| LDOTD | Permit | Temporary access, alter, or use an existing ROW |
Reviewed at the LDOTD district level. Typical timeframe for review of COMPLETE application is 45 days. |
see Details/Status |
| LDOTD | Permit | Impacts to construction affecting Louisiana Hwy 23 and for related work within LDOTD ROW |
Reviewed at the LDOTD District and HQ levels. Typical timeframe for review of a COMPLETE application is 90 days. |
see Details/Status |
| LDEQ | Certification | Section 401 Water Quality Certification | Needed prior to issuance of a 10/404 permit decision | See Details/Status |
| LDNR | CUP | Coastal Use Permit | Currently On-Hold for federal NEPA process; Needed prior to issuance of a 10/404 permit decision | see Details/Status |
Update:
The Executive Director granted a U.S. Army Corps of Engineers request to extend the Fish and Wildlife Service "Fish and Wildlife Coordination Act Review" completion date because the previous completion date was entered in error. The Executive Director determination is posted here.
-
Environmental Impact Statement (EIS)
:
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action)
- Completed Date: 09/23/2022
Issuance of Record of Decision (10/404/408). 30 days after NOA for the Final EIS and completion of the Section 408 review. One ROD for all USACE decisions.
-
Environmental Impact Statement (EIS)
:
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action)
- Completed Date: 09/23/2022
Issuance of Record of Decision (10/404/408). 30 days after NOA for the Final EIS and completion of the Section 408 review. One ROD for all USACE decisions.
Original Target Date: 06/30/2022
Milestone: Issuance of Lead Agency Record of Decision
Requested extensions greater than 30 days for this Action are shown below:
Issuance of Lead Agency Record of Decision extended by 84
From: 04/11/2022
To: 09/22/2022