Permitting Action Modification History

Complete
USACE completed their ROD ahead of schedule. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) 10-04-2013 10-04-2013 --- Yes
Scoping (Agency Action) 09-30-2017 09-05-2017 --- Yes
Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) 04-30-2020 03-05-2021 --- Yes
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) 04-30-2020 09-23-2022 --- Yes
Issuance of Lead Agency Record of Decision (Agency Action) 06-30-2022 12-19-2022 --- Yes
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) 10-04-2013 10-04-2013 --- Yes
Scoping (Agency Action) 09-30-2017 09-05-2017 --- Yes
Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) 04-30-2020 03-05-2021 --- Yes
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) 04-30-2020 09-23-2022 --- Yes
Issuance of Lead Agency Record of Decision (Agency Action) 06-30-2022 12-23-2022 --- No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) 10-04-2013 10-04-2013 --- Yes
Scoping (Agency Action) 09-30-2017 09-05-2017 --- Yes
Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) 04-30-2020 03-05-2021 --- Yes
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) 04-30-2020 09-23-2022 --- No
Issuance of Lead Agency Record of Decision (Agency Action) 06-30-2022 12-23-2022 --- No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) 10-04-2013 10-04-2013 --- Yes
Scoping (Agency Action) 09-30-2017 09-05-2017 --- Yes
Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) 04-30-2020 03-05-2021 --- Yes
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) 04-30-2020 06-24-2022 --- No
Issuance of Lead Agency Record of Decision (Agency Action) 06-30-2022 09-22-2022 --- No