USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Milestone Extension: Environmental Impact Statement (EIS)

Submitted by cori.carraway@… on

The Department’s issuance of new policies for offshore wind project reviews requires BOEM to integrate revised procedures into the NEPA process for the Vineyard Mid-Atlantic EIS. These new policies include, but are not limited to:

  • Additional time for coordination with cooperating and consulting agencies.
    • The Department’s action supports Secretary’s Order 3437 (July 29, 2025), “Ending Preferential Treatment for Unreliable, Foreign-Controlled Energy Sources in Department Decision-Making,” Secretary’s Order 3438 (August 1, 2025), “Managing Federal Energy Resources and Protecting the Environment,” and the Presidential Memorandum on wind energy signed on January 20, 2025.
  • Enhanced evaluation of energy density and land-use efficiency in alternatives analysis;
    • Secretary’s Order 3438 – Managing Federal Energy Resources and Protecting the Environment, Executive Order 14315 and SO 3437, which aim to eliminate preferential treatment for low-density, foreign-controlled energy sources
  • Updated guidance on cumulative impacts and regional energy trade-offs;
    • Secretary’s Order 3438 and the Presidential Memorandum on wind energy

The implementation of the above-mentioned policies is essential to ensure that development of the EIS is consistent with current legal and policy frameworks, and requires additional time for intra-agency coordination, stakeholder engagement, and technical analysis. These contributing factors have resulted in a 180-day delay to the development of the EIS. Therefore, the NEPA milestone dates have shifted 180-days as detailed in the table below.

Action
Project Name: Responsible Agency:
Bureau of Ocean Energy Management
Status:
In Progress
POC Name:
Lindy Nelson
POC Title:
Environmental Protection Specialist
Public Participation Website:

Milestones:

Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action)
Completed Date:
Scoping (Agency Action)
Completed Date:
Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action)
Current Target Date:
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action)
Current Target Date:
Issuance of Lead Agency Record of Decision (Agency Action)
Current Target Date:
Milestone
Issuance of Lead Agency Record of Decision (Agency Action)
Current Target Date:
Project

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
03/29/2028

0 out of 10

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Renewable Energy Production

SECTOR
Renewable Energy Production

Project Category

CATEGORY
Project Category FAST-41 Covered Projects

Department of the Interior

LEAD AGENCY
Department of the Interior, Bureau of Ocean Energy Management

View FAST-41 Postings by Agencies

Other Agencies with Actions or Authorizations:

Department of the Army

Department of the Army, US Army Corps of Engineers - Regulatory

Department of the Army

Department of the Army, US Army Corps of Engineers - Civil Works

Environmental Protection Agency

Environmental Protection Agency

Department of Commerce

Department of Commerce, National Oceanic and Atmospheric Administration

Department of the Interior

Department of the Interior, Fish and Wildlife Service

Description:

Vineyard Mid-Atlantic LLC (the “Project Sponsor”) proposes to develop, construct, and operate an offshore renewable wind energy facility in the Bureau of Ocean Energy Management’s Lease Area Outer Continental Shelf (OCS)-A 0544.  OCS-A 0544 is located approximately 38 kilometers (24 miles) offshore from Fire Island, New York. The Project would include a total of 118 wind turbine generators and offshore export cables routed to landfall sites in Long Island, New York to connect to onshore transmission systems in Nassau County, Suffolk County, and/or Queens County, New York. 

 

 

System Comments
Furthest out
Original Target Date: 06/01/2027
Milestone: Issuance of Lead Agency Record of Decision (Agency Action)

Requested extensions greater than 30 days for this Action are shown below:

Issuance of Lead Agency Record of Decision (Agency Action) extended by 181
From: 06/01/2027
To: 11/29/2027
Approver Comments
BOEM needs to make date corrections to accommodate for holidays and weekends
Missed Date Process
No
Missed Date Triggered by Extension
No
Original Milestone
Issuance of Lead Agency Record of Decision (Agency Action)
Current Target Date:
Furthest Original Target Date Milestone
Issuance of Lead Agency Record of Decision (Agency Action)
Current Target Date: