Permitting Action Modification History

In Progress
With additional BOEM and DOI reviews now required for the development of offshore wind EISs, BOEM has conducted a comprehensive status review of the established EIS schedule and found that meeting upcoming milestones is no longer feasible. The implementation of additional reviews is essential to ensure that development of the EIS is consistent with current legal and policy frameworks and requires additional time for intra-agency coordination and technical analysis. These contributing factors have resulted in a 180-day delay to the development of the EIS. Therefore, the NEPA milestone dates have shifted 180-days.  , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) 01-15-2025 01-15-2025 --- Yes
Scoping (Agency Action) 03-01-2025 03-01-2025 --- Yes
Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) 06-12-2026 06-07-2027 --- No
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) 04-16-2027 04-10-2028 --- No
Issuance of Lead Agency Record of Decision (Agency Action) 06-01-2027 05-30-2028 --- No
In Progress
The implementation of the above-mentioned policies is essential to ensure that development of the EIS is consistent with current legal and policy frameworks, and requires additional time for intra-agency coordination, stakeholder engagement, and technical analysis. These contributing factors have resulted in a 180-day delay to the development of the EIS. Therefore, the NEPA milestone dates have shifted 180-days as detailed in the table below. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) 01-15-2025 01-15-2025 --- Yes
Scoping (Agency Action) 03-01-2025 03-01-2025 --- Yes
Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) 06-12-2026 12-09-2026 --- No
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) 04-16-2027 10-13-2027 --- No
Issuance of Lead Agency Record of Decision (Agency Action) 06-01-2027 11-29-2027 --- No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) 01-15-2025 01-15-2025 --- Yes
Scoping (Agency Action) 03-01-2025 03-01-2025 --- Yes
Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) 06-12-2026 06-12-2026 --- No
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) 04-16-2027 04-16-2027 --- No
Issuance of Lead Agency Record of Decision (Agency Action) 06-01-2027 06-01-2027 --- No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) 01-15-2025 01-15-2025 --- Yes
Scoping (Agency Action) 03-01-2025 03-01-2025 --- No
Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) 06-12-2026 06-12-2026 --- No
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) 04-16-2027 04-16-2027 --- No
Issuance of Lead Agency Record of Decision (Agency Action) 06-01-2027 06-01-2027 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) 01-15-2025 01-15-2025 --- No
Scoping (Agency Action) 03-01-2025 03-01-2025 --- No
Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) 06-12-2026 06-12-2026 --- No
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) 04-16-2027 04-16-2027 --- No
Issuance of Lead Agency Record of Decision (Agency Action) 06-01-2027 06-01-2027 --- No