Permitting Action Modification History

Paused
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) 06-30-2023 06-30-2023 --- Yes
Scoping (Agency Action) 07-31-2023 07-31-2023 --- Yes
Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) 08-16-2024 08-16-2024 --- No
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) 05-16-2025 05-16-2025 --- No
Issuance of Lead Agency Record of Decision (Agency Action) 07-01-2025 07-01-2025 --- No
Paused
project pause , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) 06-30-2023 06-30-2023 --- Yes
Scoping (Agency Action) 07-31-2023 07-31-2023 --- Yes
Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) 08-16-2024 --- --- No
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) 05-16-2025 --- --- No
Issuance of Lead Agency Record of Decision (Agency Action) 07-01-2025 --- --- No
Paused
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) 06-30-2023 06-30-2023 --- Yes
Scoping (Agency Action) 07-31-2023 07-31-2023 --- Yes
Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) 08-16-2024 11-15-2024 --- No
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) 05-16-2025 08-15-2025 --- No
Issuance of Lead Agency Record of Decision (Agency Action) 07-01-2025 09-29-2025 --- No
In Progress
The project sponsor’s delayed submission of information needed for a complete Marine Mammal Protection Act (MMPA) Incidental Take Authorization (ITA) application has resulted in delays to the schedule for NMFS’s issuance of the proposed ITA as well as delays to the development of complete Endangered Species Act (ESA) and Essential Fish Habitat (EFH) consultation documents, the Draft Environmental Impact Statement (DEIS), the Final Environmental Impact Statement (FEIS) and all other subsequent dependent milestones. BOEM developed an updated permitting timetable reflecting the 90-day shift to the DEIS, FEIS, and Record of Decision (ROD) milestone dates. The NEPA Action is impacted by the milestone shifts for the ESA Action as a result of the shifts for the MMPA Action; the NEPA timeline is changing accordingly. See the explanation for the MMPA milestone shifts for more information. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) 06-30-2023 06-30-2023 --- Yes
Scoping (Agency Action) 07-31-2023 07-31-2023 --- Yes
Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) 08-16-2024 11-15-2024 --- No
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) 05-16-2025 08-15-2025 --- No
Issuance of Lead Agency Record of Decision (Agency Action) 07-01-2025 09-29-2025 --- No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) 06-30-2023 06-30-2023 --- Yes
Scoping (Agency Action) 07-31-2023 07-31-2023 --- Yes
Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) 08-16-2024 08-16-2024 --- No
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) 05-16-2025 05-16-2025 --- No
Issuance of Lead Agency Record of Decision (Agency Action) 07-01-2025 07-01-2025 --- No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) 06-30-2023 06-30-2023 --- Yes
Scoping (Agency Action) 07-31-2023 07-31-2023 --- No
Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) 08-16-2024 08-16-2024 --- No
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) 05-16-2025 05-16-2025 --- No
Issuance of Lead Agency Record of Decision (Agency Action) 07-01-2025 07-01-2025 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) 06-30-2023 06-30-2023 --- No
Scoping (Agency Action) 07-31-2023 07-31-2023 --- No
Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) 08-16-2024 08-16-2024 --- No
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) 05-16-2025 05-16-2025 --- No
Issuance of Lead Agency Record of Decision (Agency Action) 07-01-2025 07-01-2025 --- No