Permitting Action Modification History

Complete
BLM completed the milestone a week early due to internal agency factors., basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Determination to prepare an Environmental Assessment (EA) (Agency Action) 12-02-2020 12-02-2020 --- Yes
Issuance of a Final EA (Agency Action) 04-15-2026 06-15-2026 --- Yes
EA Process Concluded (Agency Action) 04-15-2026 06-15-2026 --- Yes
In Progress
The Executive Director granted a Nuclear Regulatory Commission (NRC) request to extend the final completion dates for the Section 106 consultation and the Bureau of Land Management's EA and Mine Plan of Operations on April 14, 2026. The Executive Director determination is posted to the project page., basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Determination to prepare an Environmental Assessment (EA) (Agency Action) 12-02-2020 12-02-2020 --- Yes
Issuance of a Final EA (Agency Action) 04-15-2026 06-22-2026 --- No
EA Process Concluded (Agency Action) 04-15-2026 06-22-2026 --- No
In Progress
The explanation for the milestone date change is outlined in the Executive Director Determination posted on the project page. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Determination to prepare an Environmental Assessment (EA) (Agency Action) 12-02-2020 12-02-2020 --- Yes
Issuance of a Final EA (Agency Action) 04-15-2026 05-15-2026 --- No
EA Process Concluded (Agency Action) 04-15-2026 06-22-2026 --- No
In Progress
To align with NRC and Section 106 Conclusions , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Determination to prepare an Environmental Assessment (EA) (Agency Action) 12-02-2020 12-02-2020 --- Yes
Issuance of a Final EA (Agency Action) 04-15-2026 05-15-2026 --- No
EA Process Concluded (Agency Action) 04-15-2026 05-15-2026 --- No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Determination to prepare an Environmental Assessment (EA) (Agency Action) 12-02-2020 12-02-2020 --- Yes
Issuance of a Final EA (Agency Action) 04-15-2026 04-15-2026 --- No
EA Process Concluded (Agency Action) 04-15-2026 04-15-2026 --- No