USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Permitting Action Modification History

In Progress
USACE requests extending the Section 10/404 Final Verification/Permit Decision Rendered, Issuance of a Final EA, and EA Process Concluded milestones from November 20, 2026, to May 3, 2027, to accommodate delays in the project sponsor securing the Section 401 Clean Water Act Water Quality Certification (WQC).  This schedule revision stems from the project sponsor’s delayed submission of a complete application to the Regional Water Quality Control Board (RWQCB) and a recent state court ruling that found deficiencies in Imperial County’s environmental review of the project under the California Environmental Quality Act (CEQA). Compliance with CEQA is a prerequisite for RWQCB’s WQC as mandated by 23 California Code of Regulations Section 3856. USACE cannot finalize the Section 10/404 permit decision without a valid WQC., basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Determination to prepare an Environmental Assessment (EA) (Agency Action) 08-30-2023 08-30-2023 --- Yes
Issuance of a Final EA (Agency Action) 09-01-2026 05-03-2027 --- No
EA Process Concluded (Agency Action) 09-01-2026 05-03-2027 --- No
In Progress
The Applicant recently proposed changes to the project including construction of a new permanent access road, well pad, and injection well in an entirely new footprint, resulting in the loss of approximately 12 additional acres of aquatic resources. USACE must thoroughly evaluate and address the new activities, including the potential associated impacts on federally listed species, proposed compensatory mitigation, and evaluation of cultural and tribal resources. Additionally, since the Applicant substantially modified the reasonably foreseeable impacts to aquatic resources from those described in the original public notice, USACE determined a new public notice is necessary for proper evaluation of the proposal. To complete the public notice, USACE requested additional information required by regulation. The Applicant stated they will provide the information on November 5, 2025. Once received and determined complete, USACE will issue a public notice describing the modified proposal. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Determination to prepare an Environmental Assessment (EA) (Agency Action) 08-30-2023 08-30-2023 --- Yes
Issuance of a Final EA (Agency Action) 09-01-2026 11-20-2026 --- No
EA Process Concluded (Agency Action) 09-01-2026 11-20-2026 --- No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Determination to prepare an Environmental Assessment (EA) (Agency Action) 08-30-2023 08-30-2023 --- Yes
Issuance of a Final EA (Agency Action) 09-01-2026 09-01-2026 --- No
EA Process Concluded (Agency Action) 09-01-2026 09-01-2026 --- No