USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Portions of this site may be affected due to a lapse in appropriations and associated shutdown/furloughs. Please monitor this page for updates on site availability and operating status.

Milestone Extension: Endangered Species Act Consultation (NOAA-NMFS)

Submitted by craig.litteken… on

Dates updated as part of the Original Target Dates data entry effort.

Action
Project Name: Responsible Agency:
National Oceanic and Atmospheric Administration
Agency Status: Cooperating under FAST-41
Cooperating under NEPA
Status:
Planned
POC Name:
Sue Tuxbury
POC Title:
Fishery Biologist/Wind Coordinator

Description:

Section 7(a)(2) of the Endangered Species Act (ESA) requires Federal agencies to consult with NOAA Fisheries when any action they authorize, fund, or carry out may affect an ESA-listed species or designated critical habitat under NOAA Fisheries’ jurisdiction.  ESA-listed species occur in the action area for the Revolution Wind project.  The proposed action may affect these resources, therefore Section 7 consultation is required.

Milestones:

ESA Consultation Request Package Submitted (Agency Action)
Completed Date:
Milestone Details

This target timeline is dependent on receipt of a consultation request from BOEM, consisting of a Biological Assessment, that considers effects of all proposed Federal actions.  Receipt of the consultation request is set concurrent with the beginning of the  cooperating agency review of the draft NEPA document.


NOAA determines ESA Consultation Package is Complete - Formal (Agency Action)
  • Monthly Status Report for May 2023:
    BOEM undertook a comprehensive review of the permitting timetable for this project with the cooperating agencies and project sponsor. The review encompassed all NEPA and associated agency actions and milestone dates for the project, including this action. The review culminated in a request from BOEM on May 22, 2023 for an Executive Director Determination to update interim and final completion dates for multiple actions, including this action. On May 31, 2023, the Executive Director made a determination to adjust the permitting timetable as requested, with the exception of this action. Because the Executive Director did not have enough time to make a decision more than 30 days in advance of the completion date of this action, as required under the FAST-Act (42 U.S.C. § 4370m-2(c)(2)(D)(ii)), this action was not modified through the ED Determination and instead followed the non-conformance protocol. The alternative completion date for this action, as set forth in the BOEM request to the Executive Director, was published on the dashboard.
  • Monthly Status Report for April 2023:
    NOAA confirmed on 4/3/23 that this milestone is now complete.
  • Monthly Status Report for January 2023:
    New Project information was presented by the project sponsor on October 13, 2022 to BOEM, NMFS, and the U.S. Army Corps of Engineers (USACE).  BOEM submitted a Biological Assessment to NMFS on November 1, 2022 (the date of the second ESA milestone) that did not include the new Project information.  A response letter from NMFS dated November 17, 2022 identified the additional information that was necessary to initiate consultation.  BOEM is now coordinating with the project sponsor to receive a detailed description of the new Project information to incorporate into BOEM’s biological assessment.  BOEM will submit a Biological Assessment addendum or revised Biological Assessment responsive to the information needs to NMFS by January 31, 2023. In order to provide sufficient time for NMFS to review the additional information and determine if all the information necessary for consultation has been provided (and to ensure there is time for BOEM to provide such information), prior to being locked out from future date changes on the dashboard, ESA milestone 2 is being set 60 days after BOEM’s planned information submission.  Therefore, BOEM and NOAA are requesting that ESA milestone 2 be updated from November 1, 2022 to April 3, 2023 and that ESA milestone 3 be updated to August 31, 2023.  If NMFS determines they have all of the information necessary to initiate the consultation sooner than April 3, consultation would be initiated on that earlier date; in that case, the target for completion of the ESA consultation would be 150 days after the initiation date.
  • Monthly Status Report for December 2022:
    New Project information was presented by the project sponsor on October 13, 2022 to BOEM, NMFS, and the U.S. Army Corps of Engineers (USACE).  BOEM submitted a Biological Assessment to NMFS on November 1, 2022 (the date of the second ESA milestone) that did not include the new Project information.  A response letter from NMFS dated November 17, 2022 identified the additional information that was necessary to initiate consultation.  BOEM is now coordinating with the project sponsor to receive a detailed description of the new Project information to incorporate into BOEM’s biological assessment.  BOEM will submit a Biological Assessment addendum or revised Biological Assessment responsive to the information needs to NMFS by January 31, 2023. In order to provide sufficient time for NMFS to review the additional information and determine if all the information necessary for consultation has been provided (and to ensure there is time for BOEM to provide such information), prior to being locked out from future date changes on the dashboard, ESA milestone 2 is being set 60 days after BOEM’s planned information submission.  Therefore, BOEM and NOAA are requesting that ESA milestone 2 be updated from November 1, 2022 to April 3, 2023 and that ESA milestone 3 be updated to August 31, 2023.  If NMFS determines they have all of the information necessary to initiate the consultation sooner than April 3, consultation would be initiated on that earlier date; in that case, the target for completion of the ESA consultation would be 150 days after the initiation date.
  • Non-conformance Explanation:
    New Project information was presented by the project sponsor on October 13, 2022 to BOEM, NMFS, and the U.S. Army Corps of Engineers (USACE).  BOEM submitted a Biological Assessment to NMFS on November 1, 2022 (the date of the second ESA milestone) that did not include the new Project information.  A response letter from NMFS dated November 17, 2022 identified the additional information that was necessary to initiate consultation.  BOEM is now coordinating with the project sponsor to receive a detailed description of the new Project information to incorporate into BOEM’s biological assessment.  BOEM will submit a Biological Assessment addendum or revised Biological Assessment responsive to the information needs to NMFS by January 31, 2023. In order to provide sufficient time for NMFS to review the additional information and determine if all the information necessary for consultation has been provided (and to ensure there is time for BOEM to provide such information), prior to being locked out from future date changes on the dashboard, ESA milestone 2 is being set 60 days after BOEM’s planned information submission.  Therefore, BOEM and NOAA are requesting that ESA milestone 2 be updated from November 1, 2022 to April 3, 2023 and that ESA milestone 3 be updated to August 31, 2023.  If NMFS determines they have all of the information necessary to initiate the consultation sooner than April 3, consultation would be initiated on that earlier date; in that case, the target for completion of the ESA consultation would be 150 days after the initiation date.
Current Target Date:
Milestone Details

This date is dependent upon NOAA Fisheries receiving sufficient information from BOEM to deem the package complete and initiate the ESA consultation.  This includes receipt of a complete final Biological Assessment (preferably as an appendix to the DEIS), the proposed MMPA Incidental Take Authorization from NMFS, and the public availability of the DEIS.  (Note that this date anticipates considerable coordination with BOEM on review of a draft BA).  This date is set approximately 60 days after the NOA for DEIS and no sooner than 30 days before the publication of the proposed MMPA ITA to allow adequate time to review the incoming materials and ensure receipt of complete information prior to initiation of consultation.


ESA Consultation Concludes (Agency Action)
  • Monthly Status Report for June 2023:
    NMFS anticipates meeting the July 21, 2023 milestone to conclude ESA consultation. 
  • Monthly Status Report for May 2023:
    BOEM undertook a comprehensive review of the permitting timetable for this project with the cooperating agencies and project sponsor. The review encompassed all NEPA and associated agency actions and milestone dates for the project, including this action. The review culminated in a request from BOEM on May 22, 2023 for an Executive Director Determination to update interim and final completion dates for multiple actions, including this action. On May 31, 2023, the Executive Director made a determination to adjust the permitting timetable as requested, with the exception of this action. Because the Executive Director did not have enough time to make a decision more than 30 days in advance of the completion date of this action, as required under the FAST-Act (42 U.S.C. § 4370m-2(c)(2)(D)(ii)), this action was not modified through the ED Determination and instead followed the non-conformance protocol. The alternative completion date for this action, as set forth in the BOEM request to the Executive Director, was published on the dashboard.
  • Monthly Status Report for April 2023:
    NMFS determined the consultation request package was complete and initiated the ESA consultation on March 31, 2023.
  • Non-conformance Explanation:
    New Project information was presented by the project sponsor on October 13, 2022 to BOEM, NMFS, and the U.S. Army Corps of Engineers (USACE).  BOEM submitted a Biological Assessment to NMFS on November 1, 2022 (the date of the second ESA milestone) that did not include the new Project information.  A response letter from NMFS dated November 17, 2022 identified the additional information that was necessary to initiate consultation.  BOEM coordinated with the project sponsor to receive a detailed description of the new Project information to incorporate into BOEM’s biological assessment.  BOEM submitted a revised Biological Assessment responsive to the information needs to NMFS on January 31, 2023. NMFS responded on February 16, 2023, identifying information that was missing from the January 31 Biological Assessment and is necessary to initiate consultation.  BOEM is coordinating with the project sponsor to respond and provide the requested information in an Addendum to the BA.  NMFS will review the Addendum once it is submitted; consultation will be initiated once all the necessary information has been received.  In order to provide sufficient time for NMFS to review the additional information and determine if all the information necessary for consultation has been provided (and to ensure there is time for BOEM to provide such information), prior to being locked out from future date changes on the dashboard, ESA milestone 2 was set 60 days after BOEM’s planned information submission.  Therefore, BOEM and NOAA requested that ESA milestone 2 be updated from November 1, 2022 to April 3, 2023 and that ESA milestone 3 be updated to August 31, 2023.  If NMFS determines they have all of the information necessary to initiate the consultation sooner than April 3, consultation would be initiated on that earlier date; in that case, the target for completion of the ESA consultation would be 150 days after the initiation date.
Current Target Date:
Milestone Details

The final completion date is contingent upon NOAA Fisheries receiving sufficient information that NOAA Fisheries determines adequate to initiate ESA consultation.  This date must be prior to issuance of the MMPA ITA Publication of Final Regulations (for a LOA) or MMPA Decision Rendered (if IHA) and publication of the NOA of FEIS.  The target completion date is at least 150 days following the consultation initiation date (135 day regulatory timeline plus 15 days to allow for BOEM review of the draft Opinion).

Milestone
ESA Consultation Concludes (Agency Action)
  • Monthly Status Report for June 2023:
    NMFS anticipates meeting the July 21, 2023 milestone to conclude ESA consultation. 
  • Monthly Status Report for May 2023:
    BOEM undertook a comprehensive review of the permitting timetable for this project with the cooperating agencies and project sponsor. The review encompassed all NEPA and associated agency actions and milestone dates for the project, including this action. The review culminated in a request from BOEM on May 22, 2023 for an Executive Director Determination to update interim and final completion dates for multiple actions, including this action. On May 31, 2023, the Executive Director made a determination to adjust the permitting timetable as requested, with the exception of this action. Because the Executive Director did not have enough time to make a decision more than 30 days in advance of the completion date of this action, as required under the FAST-Act (42 U.S.C. § 4370m-2(c)(2)(D)(ii)), this action was not modified through the ED Determination and instead followed the non-conformance protocol. The alternative completion date for this action, as set forth in the BOEM request to the Executive Director, was published on the dashboard.
  • Monthly Status Report for April 2023:
    NMFS determined the consultation request package was complete and initiated the ESA consultation on March 31, 2023.
  • Non-conformance Explanation:
    New Project information was presented by the project sponsor on October 13, 2022 to BOEM, NMFS, and the U.S. Army Corps of Engineers (USACE).  BOEM submitted a Biological Assessment to NMFS on November 1, 2022 (the date of the second ESA milestone) that did not include the new Project information.  A response letter from NMFS dated November 17, 2022 identified the additional information that was necessary to initiate consultation.  BOEM coordinated with the project sponsor to receive a detailed description of the new Project information to incorporate into BOEM’s biological assessment.  BOEM submitted a revised Biological Assessment responsive to the information needs to NMFS on January 31, 2023. NMFS responded on February 16, 2023, identifying information that was missing from the January 31 Biological Assessment and is necessary to initiate consultation.  BOEM is coordinating with the project sponsor to respond and provide the requested information in an Addendum to the BA.  NMFS will review the Addendum once it is submitted; consultation will be initiated once all the necessary information has been received.  In order to provide sufficient time for NMFS to review the additional information and determine if all the information necessary for consultation has been provided (and to ensure there is time for BOEM to provide such information), prior to being locked out from future date changes on the dashboard, ESA milestone 2 was set 60 days after BOEM’s planned information submission.  Therefore, BOEM and NOAA requested that ESA milestone 2 be updated from November 1, 2022 to April 3, 2023 and that ESA milestone 3 be updated to August 31, 2023.  If NMFS determines they have all of the information necessary to initiate the consultation sooner than April 3, consultation would be initiated on that earlier date; in that case, the target for completion of the ESA consultation would be 150 days after the initiation date.
Current Target Date:
Milestone Details

The final completion date is contingent upon NOAA Fisheries receiving sufficient information that NOAA Fisheries determines adequate to initiate ESA consultation.  This date must be prior to issuance of the MMPA ITA Publication of Final Regulations (for a LOA) or MMPA Decision Rendered (if IHA) and publication of the NOA of FEIS.  The target completion date is at least 150 days following the consultation initiation date (135 day regulatory timeline plus 15 days to allow for BOEM review of the draft Opinion).

Project

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
11/20/2023

9 out of 9

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Renewable Energy Production

SECTOR
Renewable Energy Production

Project Category

CATEGORY
Project Category FAST-41 Covered Projects

Department of the Interior

LEAD AGENCY
Department of the Interior, Bureau of Ocean Energy Management

View FAST-41 Postings by Agencies

Other Agencies with Actions or Authorizations:

Department of Commerce

Department of Commerce, National Oceanic and Atmospheric Administration

Department of the Army

Department of the Army, US Army Corps of Engineers - Regulatory

Environmental Protection Agency

Environmental Protection Agency

Department of the Interior

Department of the Interior, Fish and Wildlife Service

Description:

Revolution Wind LLC proposes the Revolution Wind Farm Project, an offshore wind farm to be located approximately 12 statute miles south of the coast of Rhode Island in federal waters in the area designated by the U.S. Bureau of Ocean Energy Management (BOEM) as Renewable Energy Lease Number OCS-A 0486 (the Project).

The purpose of the Project is to provide clean, reliable offshore wind energy that will increase the amount and availability of renewable energy to New England consumers while creating the opportunity to displace electricity generated by fossil fuel-powered plants and offering substantial economic and environmental benefits to the New England region. Massachusetts, Rhode Island, Connecticut, and New York have adopted substantial renewable portfolio standards and clean energy targets to address issues associated with climate change, highlighting the current and future demand for this Project.

The Project has been awarded three Power Purchase Agreements (PPAs) totaling 704 MW of generation capacity: 1) a 200 MW contract with the State of Connecticut approved in December 2018; 2) a 400 MW contract with the State of Rhode Island approved in February 2019; and 3) a 104 MW contract with the State of Connecticut approved in November 2019. The Project is being developed to fulfill its obligations to Connecticut and Rhode Island in accordance with the PPAs. The Project maximum generating capacity is 880 MW.

Update:

The Executive Director granted a Bureau of Ocean Energy Management request to extend Environmental Impact Statement, Construction and Operations Plan, and Section 106 Consultation completion dates. The Executive Director determination is posted here.

field_status
System Comments
Furthest out
Original Target Date: 01/09/2023
Milestone: ESA Consultation Concludes (Agency Action)

Requested extensions greater than 30 days for this Action are shown below:

ESA Consultation Concludes (Agency Action) extended by 81
From: 03/31/2023
To: 03/31/2023
Missed Date Process
No
Missed Date Triggered by Extension
No
Original Milestone
ESA Consultation Concludes (Agency Action)
  • Monthly Status Report for June 2023:
    NMFS anticipates meeting the July 21, 2023 milestone to conclude ESA consultation. 
  • Monthly Status Report for May 2023:
    BOEM undertook a comprehensive review of the permitting timetable for this project with the cooperating agencies and project sponsor. The review encompassed all NEPA and associated agency actions and milestone dates for the project, including this action. The review culminated in a request from BOEM on May 22, 2023 for an Executive Director Determination to update interim and final completion dates for multiple actions, including this action. On May 31, 2023, the Executive Director made a determination to adjust the permitting timetable as requested, with the exception of this action. Because the Executive Director did not have enough time to make a decision more than 30 days in advance of the completion date of this action, as required under the FAST-Act (42 U.S.C. § 4370m-2(c)(2)(D)(ii)), this action was not modified through the ED Determination and instead followed the non-conformance protocol. The alternative completion date for this action, as set forth in the BOEM request to the Executive Director, was published on the dashboard.
  • Monthly Status Report for April 2023:
    NMFS determined the consultation request package was complete and initiated the ESA consultation on March 31, 2023.
  • Non-conformance Explanation:
    New Project information was presented by the project sponsor on October 13, 2022 to BOEM, NMFS, and the U.S. Army Corps of Engineers (USACE).  BOEM submitted a Biological Assessment to NMFS on November 1, 2022 (the date of the second ESA milestone) that did not include the new Project information.  A response letter from NMFS dated November 17, 2022 identified the additional information that was necessary to initiate consultation.  BOEM coordinated with the project sponsor to receive a detailed description of the new Project information to incorporate into BOEM’s biological assessment.  BOEM submitted a revised Biological Assessment responsive to the information needs to NMFS on January 31, 2023. NMFS responded on February 16, 2023, identifying information that was missing from the January 31 Biological Assessment and is necessary to initiate consultation.  BOEM is coordinating with the project sponsor to respond and provide the requested information in an Addendum to the BA.  NMFS will review the Addendum once it is submitted; consultation will be initiated once all the necessary information has been received.  In order to provide sufficient time for NMFS to review the additional information and determine if all the information necessary for consultation has been provided (and to ensure there is time for BOEM to provide such information), prior to being locked out from future date changes on the dashboard, ESA milestone 2 was set 60 days after BOEM’s planned information submission.  Therefore, BOEM and NOAA requested that ESA milestone 2 be updated from November 1, 2022 to April 3, 2023 and that ESA milestone 3 be updated to August 31, 2023.  If NMFS determines they have all of the information necessary to initiate the consultation sooner than April 3, consultation would be initiated on that earlier date; in that case, the target for completion of the ESA consultation would be 150 days after the initiation date.
Current Target Date:
Milestone Details

The final completion date is contingent upon NOAA Fisheries receiving sufficient information that NOAA Fisheries determines adequate to initiate ESA consultation.  This date must be prior to issuance of the MMPA ITA Publication of Final Regulations (for a LOA) or MMPA Decision Rendered (if IHA) and publication of the NOA of FEIS.  The target completion date is at least 150 days following the consultation initiation date (135 day regulatory timeline plus 15 days to allow for BOEM review of the draft Opinion).

Furthest Original Target Date Milestone
ESA Consultation Concludes (Agency Action)
  • Monthly Status Report for June 2023:
    NMFS anticipates meeting the July 21, 2023 milestone to conclude ESA consultation. 
  • Monthly Status Report for May 2023:
    BOEM undertook a comprehensive review of the permitting timetable for this project with the cooperating agencies and project sponsor. The review encompassed all NEPA and associated agency actions and milestone dates for the project, including this action. The review culminated in a request from BOEM on May 22, 2023 for an Executive Director Determination to update interim and final completion dates for multiple actions, including this action. On May 31, 2023, the Executive Director made a determination to adjust the permitting timetable as requested, with the exception of this action. Because the Executive Director did not have enough time to make a decision more than 30 days in advance of the completion date of this action, as required under the FAST-Act (42 U.S.C. § 4370m-2(c)(2)(D)(ii)), this action was not modified through the ED Determination and instead followed the non-conformance protocol. The alternative completion date for this action, as set forth in the BOEM request to the Executive Director, was published on the dashboard.
  • Monthly Status Report for April 2023:
    NMFS determined the consultation request package was complete and initiated the ESA consultation on March 31, 2023.
  • Non-conformance Explanation:
    New Project information was presented by the project sponsor on October 13, 2022 to BOEM, NMFS, and the U.S. Army Corps of Engineers (USACE).  BOEM submitted a Biological Assessment to NMFS on November 1, 2022 (the date of the second ESA milestone) that did not include the new Project information.  A response letter from NMFS dated November 17, 2022 identified the additional information that was necessary to initiate consultation.  BOEM coordinated with the project sponsor to receive a detailed description of the new Project information to incorporate into BOEM’s biological assessment.  BOEM submitted a revised Biological Assessment responsive to the information needs to NMFS on January 31, 2023. NMFS responded on February 16, 2023, identifying information that was missing from the January 31 Biological Assessment and is necessary to initiate consultation.  BOEM is coordinating with the project sponsor to respond and provide the requested information in an Addendum to the BA.  NMFS will review the Addendum once it is submitted; consultation will be initiated once all the necessary information has been received.  In order to provide sufficient time for NMFS to review the additional information and determine if all the information necessary for consultation has been provided (and to ensure there is time for BOEM to provide such information), prior to being locked out from future date changes on the dashboard, ESA milestone 2 was set 60 days after BOEM’s planned information submission.  Therefore, BOEM and NOAA requested that ESA milestone 2 be updated from November 1, 2022 to April 3, 2023 and that ESA milestone 3 be updated to August 31, 2023.  If NMFS determines they have all of the information necessary to initiate the consultation sooner than April 3, consultation would be initiated on that earlier date; in that case, the target for completion of the ESA consultation would be 150 days after the initiation date.
Current Target Date:
Milestone Details

The final completion date is contingent upon NOAA Fisheries receiving sufficient information that NOAA Fisheries determines adequate to initiate ESA consultation.  This date must be prior to issuance of the MMPA ITA Publication of Final Regulations (for a LOA) or MMPA Decision Rendered (if IHA) and publication of the NOA of FEIS.  The target completion date is at least 150 days following the consultation initiation date (135 day regulatory timeline plus 15 days to allow for BOEM review of the draft Opinion).