Permitting Action Modification History

Complete
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 02-15-2022 04-25-2022 --- Yes
NOAA determines ESA Consultation Package is Complete - Formal (Agency Action) 08-01-2022 11-01-2022 03-31-2023 Yes
ESA Consultation Concludes (Agency Action) 01-09-2023 03-31-2023 07-21-2023 Yes
In Progress
Formal letter received, NMFS initiated the formal ESA section 7 consultation for the Revolution Wind project on March 31, 2023. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 02-15-2022 04-25-2022 --- Yes
NOAA determines ESA Consultation Package is Complete - Formal (Agency Action) 08-01-2022 11-01-2022 03-31-2023 Yes
ESA Consultation Concludes (Agency Action) 01-09-2023 03-31-2023 07-21-2023 No
In Progress
New Project information was presented by the project sponsor on October 13, 2022 to BOEM, NMFS, and the U.S. Army Corps of Engineers (USACE).  BOEM submitted a Biological Assessment to NMFS on November 1, 2022 (the date of the second ESA milestone) that did not include the new Project information.  A response letter from NMFS dated November 17, 2022 identified the additional information that was necessary to initiate consultation.  BOEM coordinated with the project sponsor to receive a detailed description of the new Project information to incorporate into BOEM’s biological assessment.  BOEM submitted a revised Biological Assessment responsive to the information needs to NMFS on January 31, 2023. NMFS responded on February 16, 2023, identifying information that was missing from the January 31 Biological Assessment and is necessary to initiate consultation.  BOEM is coordinating with the project sponsor to respond and provide the requested information in an Addendum to the BA.  NMFS will review the Addendum once it is submitted; consultation will be initiated once all the necessary information has been received.  In order to provide sufficient time for NMFS to review the additional information and determine if all the information necessary for consultation has been provided (and to ensure there is time for BOEM to provide such information), prior to being locked out from future date changes on the dashboard, ESA milestone 2 was set 60 days after BOEM’s planned information submission.  Therefore, BOEM and NOAA requested that ESA milestone 2 be updated from November 1, 2022 to April 3, 2023 and that ESA milestone 3 be updated to August 31, 2023.  If NMFS determines they have all of the information necessary to initiate the consultation sooner than April 3, consultation would be initiated on that earlier date; in that case, the target for completion of the ESA consultation would be 150 days after the initiation date. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 02-15-2022 04-25-2022 --- Yes
NOAA determines ESA Consultation Package is Complete - Formal (Agency Action) 08-01-2022 11-01-2022 04-03-2023 Yes
ESA Consultation Concludes (Agency Action) 01-09-2023 03-31-2023 08-31-2023 No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 02-15-2022 04-25-2022 --- Yes
NOAA determines ESA Consultation Package is Complete - Formal (Agency Action) 08-01-2022 11-01-2022 --- No
ESA Consultation Concludes (Agency Action) 01-09-2023 03-31-2023 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 02-15-2022 04-25-2022 --- Yes
NOAA determines ESA Consultation Package is Complete - Formal (Agency Action) 08-01-2022 11-01-2022 --- No
ESA Consultation Concludes (Agency Action) 01-09-2023 03-31-2023 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) --- 04-25-2022 --- Yes
NOAA determines ESA Consultation Package is Complete - Formal (Agency Action) --- 11-01-2022 --- No
ESA Consultation Concludes (Agency Action) --- 03-31-2023 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) --- 04-25-2022 --- No
NOAA determines ESA Consultation Package is Complete - Formal (Agency Action) --- 11-01-2022 --- No
ESA Consultation Concludes (Agency Action) --- 03-31-2023 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) --- 04-14-2022 --- No
NOAA determines ESA Consultation Package is Complete - Formal (Agency Action) --- 10-28-2022 --- No
ESA Consultation Concludes (Agency Action) --- 03-27-2023 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) --- 03-15-2022 --- No
NOAA determines ESA Consultation Package is Complete - Formal (Agency Action) --- 09-27-2022 --- No
ESA Consultation Concludes (Agency Action) --- 02-24-2023 --- No