Permitting Action Modification History

Planned
The ESA milestones "FWS Determines ESA Consultation Package is Complete - Formal" and "ESA Consultation Concludes" are dependent on BOEM’s EIS action milestones. A shift of BOEM’s EIS action milestones by 180 days results in a commensurate shift to these ESA action milestones.  Therefore, an extension is requested based upon the extension of BOEM’s EIS milestones. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 06-12-2026 06-07-2027 --- No
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) 07-12-2026 07-07-2027 --- No
ESA Consultation Concludes (Agency Action) 11-24-2026 11-22-2027 --- No
Planned
The ESA milestones "FWS Determines ESA Consultation Package is Complete - Formal" and "ESA Consultation Concludes" are dependent on BOEM’s EIS action milestones. A shift of BOEM’s EIS action milestones by 180 days results in a commensurate shift to these ESA action milestones. Therefore, an extension is requested based upon the extension of BOEM’s EIS milestones. The requested milestone changes are shown in the table below. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 06-12-2026 12-09-2026 --- No
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) 07-12-2026 01-08-2027 --- No
ESA Consultation Concludes (Agency Action) 11-24-2026 05-24-2027 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 06-12-2026 06-12-2026 --- No
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) 07-12-2026 07-12-2026 --- No
ESA Consultation Concludes (Agency Action) 11-24-2026 11-24-2026 --- No