Permitting Action Modification History

Cancelled
The ESA milestones are dependent on BOEM’s EIS action milestones. A shift of BOEM’s EIS action milestones by 417 days results in a commensurate shift to the ESA action milestones.  Therefore, an extension of the ESA milestones is requested based upon the extension of BOEM’s COP and EIS milestones. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 08-21-2026 05-24-2027 --- No
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) 11-19-2026 08-20-2027 --- No
ESA Consultation Concludes (Agency Action) 04-19-2027 01-18-2028 --- No
Planned
BOEM is requesting these completion date modifications due to the timing of the Project Sponsor’s submission of a revised Construction and Operations Plan (COP) containing additional data and assessments that BOEM requires prior to issuing a Notice of Intent (NOI) to prepare an Environmental Impact Statement (EIS) under NEPA. BOEM has requested that the revised COP contain certain survey data for one of the proposed cable routes as well as the following assessments: the Navigational Safety Risk Assessment; Historic Resources Visual Effects Assessment for certain facilities; Marine Archaeological Resource Assessment for a particular cable route; and the Terrestrial Archeological Resource Assessment for all routes and facilities in the onshore project design envelope. The Project Sponsor intends to submit the revised COP containing all the requested information on October 27, 2025.  The timing of ESA consultation with FWS is dependent on the timing of the NEPA process.  The date for receipt of a consultation request is set to be shortly after issuance of the DEIS. The remaining dates for ESA consultation flow from the date that consultation is initiated. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 08-21-2026 05-24-2027 --- No
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) 11-19-2026 08-20-2027 --- No
ESA Consultation Concludes (Agency Action) 04-19-2027 01-18-2028 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 08-21-2026 08-21-2026 --- No
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) 11-19-2026 11-19-2026 --- No
ESA Consultation Concludes (Agency Action) 04-19-2027 04-19-2027 --- No