USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Milestone Extension: Construction and Operations Plan

Submitted by jennifer.malla… on

This new schedule accommodates the later submission of the initial MMPA permit application.

Action
Project Name: Responsible Agency:
Bureau of Ocean Energy Management
Status:
In Progress
POC Name:
Jennifer Bucatari
POC Title:
Environmental Coordinator

Milestones:

Initial application submitted (Applicant Action)
Completed Date:
Application deemed complete (Agency Action)
Completed Date:
Final decision/agency action (Agency Action)
Current Target Date:
Milestone
Final decision/agency action (Agency Action)
Current Target Date:
Project

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING

0 out of 0

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Renewable Energy Production

SECTOR
Renewable Energy Production

Project Category

CATEGORY
Project Category FAST-41 Covered Projects

Department of the Interior

LEAD AGENCY
Department of the Interior, Bureau of Ocean Energy Management

View FAST-41 Postings by Agencies

Description:

Update: In June 2022, the project name changed from Kitty Hawk Wind Project to Kitty Hawk North Wind Project to reflect the segmenting of the project.

The purpose of the Kitty Hawk North Wind Project is to develop a commercial-scale, offshore wind energy facility in Commercial Lease OCS-A 0508 offshore North Carolina, with up to 69 total wind turbine generators, 1 offshore substation (also called “electrical service platform”), inter-array cables, 1 onshore substation, and up to 2 transmission cables making landfall in Virginia Beach, Virginia, and connecting to the Pennsylvania-New Jersey-Maryland (PJM) Interconnection energy grid. Kitty Hawk is actively seeking one or more power purchase agreement awards for this project. The project is intended to substantially contribute to the region’s electrical reliability and help Virginia achieve its renewable energy goals as stated in the Virginia Clean Economy Act.

FAST-41 provides increased transparency and predictability by requiring Federal agencies to publish comprehensive permitting timetables for all "covered" projects, and provides clear procedures for modifying permitting timetables to address the unpredictability inherent in the environmental review and permitting process for significant infrastructure projects. For more information, see "The FAST-41 Process" at  https://www.permits.performance.gov/fpisc-content/fast-41-process

field_status
System Comments
Furthest out
Original Target Date: 11/01/2023
Milestone: Final decision/agency action (Agency Action)

Requested extensions greater than 30 days for this Action are shown below:

Final decision/agency action (Agency Action) extended by 579
From: 11/01/2023
To: 06/02/2025
Approver Comments
ED Review completed and final signed 5/12/2023.
Missed Date Process
No
Missed Date Triggered by Extension
No
Original Milestone
Final decision/agency action (Agency Action)
Current Target Date:
Furthest Original Target Date Milestone
Final decision/agency action (Agency Action)
Current Target Date: