Permitting Action Modification History

Cancelled
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 12-11-2020 12-11-2020 --- Yes
Application deemed complete (Agency Action) 07-30-2021 07-30-2021 --- Yes
Final decision/agency action (Agency Action) 11-01-2023 08-17-2026 --- No
In Progress
The COP milestone is dependent on the NEPA schedule and will shift accordingly. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 12-11-2020 12-11-2020 --- Yes
Application deemed complete (Agency Action) 07-30-2021 07-30-2021 --- Yes
Final decision/agency action (Agency Action) 11-01-2023 08-17-2026 --- No
In Progress
This new schedule accommodates the later submission of the initial MMPA permit application. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 12-11-2020 12-11-2020 --- Yes
Application deemed complete (Agency Action) 07-30-2021 07-30-2021 --- Yes
Final decision/agency action (Agency Action) 11-01-2023 06-02-2025 --- No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 12-11-2020 12-11-2020 --- Yes
Application deemed complete (Agency Action) 07-30-2021 07-30-2021 --- Yes
Final decision/agency action (Agency Action) 11-01-2023 11-01-2023 --- No