USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Permitting Action Modification History

Cancelled
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 12-11-2020 12-11-2020 --- Yes
Application deemed complete (Agency Action) 07-30-2021 07-30-2021 --- Yes
Final decision/agency action (Agency Action) 11-01-2023 08-17-2026 --- No
In Progress
The COP milestone is dependent on the NEPA schedule and will shift accordingly.
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 12-11-2020 12-11-2020 --- Yes
Application deemed complete (Agency Action) 07-30-2021 07-30-2021 --- Yes
Final decision/agency action (Agency Action) 11-01-2023 08-17-2026 --- No
In Progress
This new schedule accommodates the later submission of the initial MMPA permit application.
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 12-11-2020 12-11-2020 --- Yes
Application deemed complete (Agency Action) 07-30-2021 07-30-2021 --- Yes
Final decision/agency action (Agency Action) 11-01-2023 06-02-2025 --- No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 12-11-2020 12-11-2020 --- Yes
Application deemed complete (Agency Action) 07-30-2021 07-30-2021 --- Yes
Final decision/agency action (Agency Action) 11-01-2023 11-01-2023 --- No