Permitting Action Modification History

Complete
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 07-20-2020 07-02-2020 --- Yes
Application deemed complete (Agency Action) 12-15-2020 12-15-2020 --- Yes
Final decision/agency action (Agency Action) 10-01-2023 07-01-2024 --- Yes
In Progress
BOEM needs to two weeks after ESA consultation concludes to incorporate the completed ESA consultation in the Final Environmental Impact Statement. Therefore, BOEM is updating the FEIS milestone to March 1, 2024. ROD issuance and COP decision dates are dependent on the FEIS milestone, and so these milestone dates are also shifting by 98-days to April 1, 2024, and July 1, 2024, respectively. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 07-20-2020 07-02-2020 --- Yes
Application deemed complete (Agency Action) 12-15-2020 12-15-2020 --- Yes
Final decision/agency action (Agency Action) 10-01-2023 07-01-2024 --- No
In Progress
The COP final completion date is dependent upon the final completion date of BOEM’s NEPA action. BOEM requests that the COP final completion date be extended 90 days beyond the final completion date for the ROD. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 07-20-2020 07-02-2020 --- Yes
Application deemed complete (Agency Action) 12-15-2020 12-15-2020 --- Yes
Final decision/agency action (Agency Action) 10-01-2023 03-25-2024 --- No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 07-20-2020 07-02-2020 --- Yes
Final decision/agency action (Agency Action) 10-01-2023 10-01-2023 --- No