Milestone Extension: Construction and Operations Plan

Submitted by cori.carraway@… on

Because the COP final completion date is contingent on issuance of the ROD, BOEM requests that the COP final completion date be extended by 30 days, to February 21, 2024 due to the ROD moving to November 21, 2023.

Action
Project Name: Responsible Agency:
Bureau of Ocean Energy Management
Status:
In Progress
POC Name:
Brandi Sangunett
POC Title:
Environmental Protection Specialist

Milestones:

Initial application submitted (Applicant Action)
Completed Date:
Application deemed complete (Agency Action)
Completed Date:
Final decision/agency action (Agency Action)
Current Target Date:
Milestone
Final decision/agency action (Agency Action)
Current Target Date:
Project

PROJECT WEBSITE: Equinor's Empire Wind

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
03/11/2024

10 out of 10

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Renewable Energy Production

SECTOR
Renewable Energy Production

Project Category

CATEGORY
Project Category FAST-41 Covered Projects

Department of the Interior

LEAD AGENCY
Department of the Interior, Bureau of Ocean Energy Management

View FAST-41 Postings by Agencies

Other Agencies with Actions or Authorizations:

Department of the Army

Department of the Army, US Army Corps of Engineers - Civil Works

Department of the Army

Department of the Army, US Army Corps of Engineers - Regulatory

Department of Commerce

Department of Commerce, National Oceanic and Atmospheric Administration

Department of the Interior

Department of the Interior, Fish and Wildlife Service

Environmental Protection Agency

Environmental Protection Agency

Description:

Equinor Wind proposes to construct and operate the Empire Wind Energy Project located in Lease Area OCS-A 0512, which covers approximately 79,350 acres (ac; 32,112 hectares [ha]) and is located approximately 14 statute miles (mi) (12 nautical miles [nm], 22 kilometers [km]) south of Long Island, New York and 19.5 mi (16.9 nm, 31.4 km) east of Long Branch, New Jersey.  The project includes development of the lease area in two wind farms, known as Empire Wind 1 (EW 1) and Empire Wind 2 (EW 2). EW 1 and EW 2 will be electrically isolated and independent from each other. Empire Wind proposes to construct and operate up to 147 wind turbines and up to 2 offshore substations with 2 cable routes under the terms of the Renewable Energy Lease.

 

The Executive Director granted a Bureau of Ocean Energy Management (BOEM) request to extend the EIS, COP, Section 106, ESA, EFH, Section 10/404 completion date on March 23, 2023. The Executive Director determination is posted here.

 

The Executive Director granted a Bureau of Ocean Energy Management (BOEM) request to extend the OCS Air Permit completion date on September 06, 2023. The Executive Director determination is posted here.

 

field_status
System Comments
Furthest out
Original Target Date: 09/08/2023
Milestone: Final decision/agency action (Agency Action)

Requested extensions greater than 30 days for this Action are shown below:

Final decision/agency action (Agency Action) extended by 166
From: 01/22/2024
To: 02/21/2024
Approver Comments
Exec. Director Determination completed on 11/2/2023
Missed Date Process
No
Missed Date Triggered by Extension
No
Original Milestone
Final decision/agency action (Agency Action)
Current Target Date:
Furthest Original Target Date Milestone
Final decision/agency action (Agency Action)
Current Target Date: