USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Milestone Extension: Clean Water Act Section 402 Permit, National Pollutant Discharge Elimination System (EPA)

Submitted by cori.carraway@… on

The NPDES Permit milestones are dependent on BOEM's EIS action milestones. With the shift in the ROD date, EPA will accordingly extend the milestone date for issuance of the final decision for permit/approval of the Clean Water Act Section 402 permit. This enables EPA to ensure compliance with ESA and with other laws, such as those related to Essential Fish Habitat (EFH).

Action
Project Name: Responsible Agency:
Environmental Protection Agency
Agency Status: Cooperating under FAST-41
Status:
In Progress
POC Name:
Sharon DeMeo
POC Title:
Region 1 NPDES lead

Milestones:

Initial application received (Applicant Action)
Completed Date:
Completed application received (Applicant Action)
Current Target Date:
EPA authorizes discharge under Individual permit (Agency Action)
Current Target Date:
Milestone
EPA authorizes discharge under Individual permit (Agency Action)
Current Target Date:
Project

PROJECT WEBSITE: Vineyard Offshore

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
11/09/2026

0 out of 10

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Renewable Energy Production

SECTOR
Renewable Energy Production

Project Category

CATEGORY
Project Category FAST-41 Covered Projects

Department of the Interior

LEAD AGENCY
Department of the Interior, Bureau of Ocean Energy Management

View FAST-41 Postings by Agencies

Other Agencies with Actions or Authorizations:

Department of Commerce

Department of Commerce, National Oceanic and Atmospheric Administration

Department of the Interior

Department of the Interior, Fish and Wildlife Service

Department of the Army

Department of the Army, US Army Corps of Engineers - Regulatory

Environmental Protection Agency

Environmental Protection Agency

Description:

Vineyard Northeast proposes to construct and operate the Project located in Lease Area OCS-A 0522, which covers approximately 132,370 acres (ac) and is located approximately 31 miles from Nantucket, Massachusetts and 39 miles from Martha’s Vineyard, Massachusetts.

Offshore components of the Project will consist of up to 160 wind turbine generators (WTG) and electrical service platform (ESP) positions within the Lease Area with one nautical mile spacing between positions. The WTGs and ESPs will be supported by monopiles or piled jacket foundations.

Between the Lease Area and shore, the offshore export cables will be installed within two offshore export cable corridors (OECC), the Massachusetts OECC and the Connecticut OECC.

    • The Massachusetts OECC will travel from the northernmost tip of the Lease Area to the Horseneck Beach Landfall site in Westport, Massachusetts.
    • The Connecticut OECC will travel from the southernmost tip of the Lease Area to three potential landfall sites: Eastern Point Beach, Ocean Beach, and Niantic Beach; all near New London, Connecticut.

Onshore components of the Project will include export cable landfall areas, high-voltage direct current onshore cables, high-voltage alternating current interconnection cables, converter and booster stations, and onshore substation facilities in Massachusetts and Connecticut. 

field_status
System Comments
Furthest out
Original Target Date: 06/23/2026
Milestone: EPA authorizes discharge under Individual permit (Agency Action)

Requested extensions greater than 30 days for this Action are shown below:

EPA authorizes discharge under Individual permit (Agency Action) extended by 119
From: 06/23/2026
To: 10/20/2026
Approver Comments
EDD Signed 4/18/2025 granting movement
Missed Date Process
No
Missed Date Triggered by Extension
No
Original Milestone
EPA authorizes discharge under Individual permit (Agency Action)
Current Target Date:
Furthest Original Target Date Milestone
EPA authorizes discharge under Individual permit (Agency Action)
Current Target Date: