USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Milestone Extension: Clean Water Act Section 402 Permit, National Pollutant Discharge Elimination System (EPA)

Submitted by craig.litteken… on

The project sponsor provided BOEM notice on June 26, 2023 of plans to initiate onshore construction activities. The notice provided information on their planned work at the Onshore Converter Station and laydown yards (Phase 1A activities, scheduled to start around July 10), and installation of splice vaults and duct banks, and the expansion of an existing substation (Phase 1B activities, scheduled to commence around September). BOEM notified Tribal Nations, cooperating agencies, Section 106 consulting parties, and the project sponsor that BOEM did not have authority over these activities and that onshore construction would be moving forward.  While BOEM does not have authority over these onshore activities, BOEM has a responsibility to analyze impacts from all the proposed onshore activities included within the scope of a project as connected actions under the National Environmental Policy Act (NEPA) and Section 106 of the National Historic Preservation Act (NHPA). A Construction and Operations Plan (COP) update was required to move forward with these analyses because the prior COP dated August 18, 2022, did not include enough detailed information regarding the onshore activities. The project sponsor submitted an updated COP to BOEM on September 29, 2023. The updated information was necessary for determining the timeline for concluding the Section 106 process and Record of Decision.  Movement of the ROD is therefore causing movement of this dependent action.

Action
Project Name: Responsible Agency:
Environmental Protection Agency
Agency Status: Cooperating under FAST-41
Status:
In Progress
POC Name:
Danielle Gaito

Description:

The NPDES program is authorized by CWA: Section 402 (40 CFR Part 122). NPDES permits control discharges to waters of the U.S. The program ensures that discharges meet state water quality standards and other Clean Water Act requirements.  A NPDES permit is required because the applicant proposes to withdraw cooling water from and discharge pollutants to the Atlantic Ocean from one or more offshore substations.

Milestones:

Initial application received (Applicant Action)
Completed Date:
Completed application received (Applicant Action)
Completed Date:
Issuance of final decision/ permit approval (Agency Action)
Current Target Date:
Milestone
Issuance of final decision/ permit approval (Agency Action)
Current Target Date:
Project

PROJECT WEBSITE: https://www.boem.gov/Sunrise-Wind

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
06/21/2024

12 out of 12

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Renewable Energy Production

SECTOR
Renewable Energy Production

Project Category

CATEGORY
Project Category FAST-41 Covered Projects

Department of the Interior

LEAD AGENCY
Department of the Interior, Bureau of Ocean Energy Management

View FAST-41 Postings by Agencies

Other Agencies with Actions or Authorizations:

Department of Commerce

Department of Commerce, National Oceanic and Atmospheric Administration

Department of the Interior

Department of the Interior, Fish and Wildlife Service

Environmental Protection Agency

Environmental Protection Agency

Department of the Army

Department of the Army, US Army Corps of Engineers - Regulatory

Department of the Interior

Department of the Interior, National Park Service

Department of the Army

Department of the Army, US Army Corps of Engineers - Civil Works

Description:

Sunrise Wind LLC (Sunrise Wind) proposes to construct, operate and maintain an offshore wind farm to be located approximately 18.5 statute miles (mi) (16.1 nautical miles [nm], 29.8 kilometers [km]) south of Martha’s Vineyard, Massachusetts, and approximately 30 mi (26.1 nm, 48.2 km) east of Montauk, New York (NY). The majority of the Project would be located in federal waters in the designated Bureau of Ocean Energy Management (BOEM) Renewable Energy Lease Area OCS-A 0487.

Update:

The Executive Director granted a BOEM request to extend the Construction and Operations Plan (COP) completion date on November 16, 2021. The Executive Director determination is posted here.

The Executive Director granted a BOEM request to extend the NEPA, COP, Section 106, MMPA (NOAANMFS), Sections 10/404/408 (USACE), NPS Permit (NPS), Clean Water Act Section 402 (EPA), and OCS Air Permit (EPA) completion dates on June 6, 2023. The Executive Director determination is posted here.

field_status
System Comments
Furthest out
Original Target Date: 09/29/2023
Milestone: EPA authorizes discharge under Individual permit (Agency Action)

Requested extensions greater than 30 days for this Action are shown below:

EPA authorizes discharge under Individual permit (Agency Action) extended by 266
From: 03/04/2024
To: 06/21/2024
Approver Comments
Executive Director Determination signed on 2/2/24.
Missed Date Process
No
Missed Date Triggered by Extension
No
Original Milestone
Issuance of final decision/ permit approval (Agency Action)
Current Target Date:
Furthest Original Target Date Milestone
Issuance of final decision/ permit approval (Agency Action)
Current Target Date: