USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Permitting Action Modification History

In Progress
Project Sponsor's representative submitted all construction drawings required to complete the application., basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 02-19-2026 02-19-2026 --- Yes
Application deemed complete (Agency Action) 07-21-2026 09-18-2026 10-06-2026 Yes
Final decision/agency action (Agency Action) 08-20-2026 10-19-2026 --- No
Planned
Reclamation continues to work with Sacred Wind and their team to finalize accurate construction drawings for the project required for Reclamation to deem the application complete. Reclamation sent comments on the last set of drawings received from the project sponsor's designee on 9/29. The comments were not extensive so Reclamation anticipates approximately a week for the designee to allow them sufficient time to prepare final accurate drawing allowing Reclamation to deem the application complete on 10/8., basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 02-19-2026 02-19-2026 --- Yes
Application deemed complete (Agency Action) 07-21-2026 09-18-2026 10-08-2026 No
Final decision/agency action (Agency Action) 08-20-2026 10-19-2026 --- No
Planned
While the Project Sponsor has been responsive to requests for the required information, the applications provided by the May 22, 2026 milestone were not complete. The milestones are dependent on all outstanding application materials being submitted by the applicant, so the milestones are being shifted by 60 days to allow time to review the complete applications once received., basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 02-19-2026 02-19-2026 --- Yes
Application deemed complete (Agency Action) 07-21-2026 09-18-2026 --- No
Final decision/agency action (Agency Action) 08-20-2026 10-19-2026 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 02-19-2026 02-19-2026 --- Yes
Application deemed complete (Agency Action) 07-21-2026 07-21-2026 --- No
Final decision/agency action (Agency Action) 08-20-2026 08-20-2026 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 02-19-2026 02-19-2026 --- No
Application deemed complete (Agency Action) 07-21-2026 07-21-2026 --- No
Final decision/agency action (Agency Action) 08-20-2026 08-20-2026 --- No