Permitting Action Modification History
Modifications on 11/02/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Initial application submitted (Applicant Action) | 02-19-2026 | 02-19-2026 | --- | Yes |
| Application deemed complete (Agency Action) | 07-21-2026 | 09-18-2026 | 10-06-2026 | Yes |
| Final decision/agency action (Agency Action) | 08-20-2026 | 10-19-2026 | 10-30-2026 | Yes |
Modifications on 10/06/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Initial application submitted (Applicant Action) | 02-19-2026 | 02-19-2026 | --- | Yes |
| Application deemed complete (Agency Action) | 07-21-2026 | 09-18-2026 | 10-06-2026 | Yes |
| Final decision/agency action (Agency Action) | 08-20-2026 | 10-19-2026 | --- | No |
Modifications on 10/01/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Initial application submitted (Applicant Action) | 02-19-2026 | 02-19-2026 | --- | Yes |
| Application deemed complete (Agency Action) | 07-21-2026 | 09-18-2026 | 10-08-2026 | No |
| Final decision/agency action (Agency Action) | 08-20-2026 | 10-19-2026 | --- | No |
Modifications on 06/19/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Initial application submitted (Applicant Action) | 02-19-2026 | 02-19-2026 | --- | Yes |
| Application deemed complete (Agency Action) | 07-21-2026 | 09-18-2026 | --- | No |
| Final decision/agency action (Agency Action) | 08-20-2026 | 10-19-2026 | --- | No |
Modifications on 04/30/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Initial application submitted (Applicant Action) | 02-19-2026 | 02-19-2026 | --- | Yes |
| Application deemed complete (Agency Action) | 07-21-2026 | 07-21-2026 | --- | No |
| Final decision/agency action (Agency Action) | 08-20-2026 | 08-20-2026 | --- | No |
Modifications on 04/30/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Initial application submitted (Applicant Action) | 02-19-2026 | 02-19-2026 | --- | No |
| Application deemed complete (Agency Action) | 07-21-2026 | 07-21-2026 | --- | No |
| Final decision/agency action (Agency Action) | 08-20-2026 | 08-20-2026 | --- | No |