FAST-41 Missed Date:Special Use Permit (FS): Final decision/agency action (Agency Action)

Submitted by Anonymous on

Agency Milestone Date of 05/13/2026 for Final decision/agency action (Agency Action) has passed by 1 business days

Action
Project Name: Responsible Agency:
US Forest Service
Status:
In Progress
POC Name:
Kimpton Cooper
POC Title:
Forest Supervisor, National Forests and Grasslands in Texas

Milestones:

Initial application submitted (Applicant Action)
Completed Date:
Application deemed complete (Agency Action)
Completed Date:
Final decision/agency action (Agency Action)
Current Target Date:
Milestone
Final decision/agency action (Agency Action)
Current Target Date:
Project

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
05/15/2026

5 out of 6

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Pipelines

SECTOR
Pipelines

Project Category

CATEGORY
Project Category FAST-41 Covered Projects

Department of Agriculture

LEAD AGENCY
Department of Agriculture, US Forest Service

View FAST-41 Postings by Agencies

Description:

Silver Hill Energy is proposing to build a natural gas trunk pipeline through the Sabine National Forest along with four drilling well pads to develop their existing Federal mineral leases.  The project area is located in Shelby County, TX, directly east of the town of Goober Hill, TX. 

field_status
System Comments
Agency Milestone Date of 05/13/2026 for Final decision/agency action (Agency Action) has passed by 1 business days
Approver Comments
<p><span data-teams="true">An executable Special Use Permit for an Oil or Gas Facility for the Cobra Master Development Plan Project was delivered to the project sponsor on the target completion date of May 13, 2026. The project sponsor declined to sign on the target completion date, owing to the absence of appendices that were still pending delivery by the project sponsor’s contractor and review and approval by the Forest. It was the project sponsor’s stated preference that the permit not be executed until after inclusion of all approved appendices. The Forest is actively reviewing all deliverables received on May 19, 2026, and working towards a revised issuance of the Special Use Permit with appendices. The Forest is working with the project sponsor to identify an alternative completion date.</span></p>
Previous Action Status
New Action Status
Missed Date Process
Yes
Missed Date Triggered by Extension
No
New Milestone
Final decision/agency action (Agency Action)
Current Target Date: