Permitting Action Modification History

Complete
Finished final milestone 4 days ahead of schedule from 1/15/26 to 1/12/26.  , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 07-15-2025 07-15-2025 --- Yes
Completeness Determination (Agency Action) 08-15-2025 08-13-2025 --- Yes
Complete application submitted (Applicant Action) 10-15-2025 10-15-2025 --- Yes
Issuance of Decision (Agency Action) 01-15-2026 01-12-2026 --- Yes
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 07-15-2025 07-15-2025 --- Yes
Completeness Determination (Agency Action) 08-15-2025 08-13-2025 --- Yes
Complete application submitted (Applicant Action) 10-15-2025 10-15-2025 --- Yes
Issuance of Decision (Agency Action) 01-15-2026 01-15-2026 --- No
In Progress
The completeness determination milestone was completed 2 days ahead of the current schedule. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 07-15-2025 07-15-2025 --- Yes
Completeness Determination (Agency Action) 08-15-2025 08-13-2025 --- Yes
Complete application submitted (Applicant Action) 10-15-2025 10-15-2025 --- No
Issuance of Decision (Agency Action) 01-15-2026 01-15-2026 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 07-15-2025 07-15-2025 --- Yes
Completeness Determination (Agency Action) 08-15-2025 08-15-2025 --- No
Complete application submitted (Applicant Action) 10-15-2025 10-15-2025 --- No
Issuance of Decision (Agency Action) 01-15-2026 01-15-2026 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 07-15-2025 07-15-2025 --- No
Complete application submitted (Applicant Action) 10-15-2025 10-15-2025 --- No
Issuance of Decision (Agency Action) 01-15-2026 01-15-2026 --- No