FAST-41 Missed Date:Section 106 Review: Consultation initiated with SHPO/THPO (Agency Action)

Submitted by Anonymous on

Agency Milestone Date of 05/15/2026 for Consultation initiated with SHPO/THPO (Agency Action) has passed by 1 business days

Action
Project Name: Responsible Agency:
Bureau of Reclamation
Status:
Planned
POC Name:
Marielle Black
POC Email:

Milestones:

Consultation initiated with SHPO/THPO (Agency Action)
  • Non-conformance Explanation:
    The Bureau of Reclamation missed the May 15, 2026, milestone to initiate National Historic Preservation Act Section 106 review. In preliminary review of the draft cultural resource inventory report, comments were received May 4, 2026 requiring additional time to determine the ultimate path forward. Revisions were still in progress when the milestone date was reached.
Current Target Date:
Section 106 consultation concluded (Agency Action)
Current Target Date:
Milestone
Consultation initiated with SHPO/THPO (Agency Action)
  • Non-conformance Explanation:
    The Bureau of Reclamation missed the May 15, 2026, milestone to initiate National Historic Preservation Act Section 106 review. In preliminary review of the draft cultural resource inventory report, comments were received May 4, 2026 requiring additional time to determine the ultimate path forward. Revisions were still in progress when the milestone date was reached.
Current Target Date:
Project

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
04/28/2028

0 out of 3

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Electricity Transmission

SECTOR
Electricity Transmission

Project Category

CATEGORY
Project Category FAST-41 Covered Projects

Department of the Interior

LEAD AGENCY
Department of the Interior, Bureau of Reclamation

View FAST-41 Postings by Agencies

Description:

Clearway Energy Group requests a land use authorization license from the Bureau of Reclamation to construct, operate, and maintain electrical power transmission lines and associated access roads on Reclamation-administered land.  The 230-kilovolt electrical power transmission line would transmit electricity from a solar power generation facility on private land, across Reclamation-administered land, to the Vantage Substation in Grant County, Washington. This Project will serve electricity users in Washington, with the target of serving Grant County specifically. 

 
 
 
field_status
System Comments
Agency Milestone Date of 05/15/2026 for Consultation initiated with SHPO/THPO (Agency Action) has passed by 1 business days
Approver Comments
<p>The Bureau of Reclamation (Reclamation) missed the May 15, 2026, milestone to initiate National Historic Preservation Act Section 106 review. Per 42 U.S.C.§ 4370m-2(c)(2)(F), Reclamation is required to provide an alternative completion date and an initial explanation for the missed completion date by May 22, 2026. Reclamation has provided the initial explanation for the missed date, but has not yet provided the required alternative completion date. The Permitting Council is working with Reclamation to ensure an alternative completion date is determined and represented on the permitting timetable as soon as possible. In preliminary review of the draft cultural resource inventory report, comments were received May 4, 2026 and provided to the Project Sponsor requiring them to revise the document. Revisions were still in progress when the milestone date was reached.&nbsp;</p>
Previous Action Status
New Action Status
Missed Date Process
Yes
Missed Date Triggered by Extension
No
Agency Notified Date
New Milestone
Consultation initiated with SHPO/THPO (Agency Action)
  • Non-conformance Explanation:
    The Bureau of Reclamation missed the May 15, 2026, milestone to initiate National Historic Preservation Act Section 106 review. In preliminary review of the draft cultural resource inventory report, comments were received May 4, 2026 requiring additional time to determine the ultimate path forward. Revisions were still in progress when the milestone date was reached.
Current Target Date:
Response Date
Reporting Agency