FAST-41 Missed Date:Section 106 Review: Consultation initiated with SHPO/THPO (Agency Action)

Submitted by Anonymous on

Agency Milestone Date of 05/15/2026 for Consultation initiated with SHPO/THPO (Agency Action) has passed by 1 business days

Action
Milestone
Consultation initiated with SHPO/THPO (Agency Action)
Current Target Date:
Project

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
04/28/2028

0 out of 3

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Electricity Transmission

SECTOR
Electricity Transmission

Project Category

CATEGORY
Project Category FAST-41 Covered Projects

Department of the Interior

LEAD AGENCY
Department of the Interior, Bureau of Reclamation

View FAST-41 Postings by Agencies

Description:

Clearway Energy Group requests a land use authorization license from the Bureau of Reclamation to construct, operate, and maintain electrical power transmission lines and associated access roads on Reclamation-administered land.  The 230-kilovolt electrical power transmission line would transmit electricity from a solar power generation facility on private land, across Reclamation-administered land, to the Vantage Substation in Grant County, Washington. This Project will serve electricity users in Washington, with the target of serving Grant County specifically. 

 
 
 
field_status
System Comments
Agency Milestone Date of 05/15/2026 for Consultation initiated with SHPO/THPO (Agency Action) has passed by 1 business days
Previous Action Status
New Action Status
Missed Date Process
Yes
Missed Date Triggered by Extension
No
New Milestone
Consultation initiated with SHPO/THPO (Agency Action)
Current Target Date:
Response Date
Reporting Agency