Permitting Action Modification History

In Progress
Section 106 consultation concluded milestone change to reflect current targeted completion of the 106 process as outlined in Interior Secretary's Order 3452., basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Consultation initiated with SHPO/THPO (Agency Action) 05-15-2026 05-15-2026 06-15-2026 Yes
Section 106 consultation concluded (Agency Action) 04-13-2028 04-13-2028 01-11-2027 No
In Progress
Reclamation was able to initiate the 106 consultation earlier than the previously published 6/30/2026 Alternative Completion Date by expediting the finalization of the consultation materials and internal approvals of the consultation materials., basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Consultation initiated with SHPO/THPO (Agency Action) 05-15-2026 05-15-2026 06-15-2026 Yes
Section 106 consultation concluded (Agency Action) 04-13-2028 04-13-2028 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Consultation initiated with SHPO/THPO (Agency Action) 05-15-2026 05-15-2026 06-30-2026 No
Section 106 consultation concluded (Agency Action) 04-13-2028 04-13-2028 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Consultation initiated with SHPO/THPO (Agency Action) 05-15-2026 05-15-2026 --- No
Section 106 consultation concluded (Agency Action) 04-13-2028 04-13-2028 --- No